Percepatan Waktu Pelaksanaan Pembangunan Gedung Rumah Sakit Aisyiyah Kabupaten Ponorogo Menggunakan Metode PERT (Program Evaluation and Review Technique)

Authors

  • Ilham Juniar Abraham Faculty of Engineering, Kadiri University
  • Ahmad Ridwan Faculty of Engineering, Kadiri University
  • Suwarno Suwarno Faculty of Engineering, Kadiri University

DOI:

https://doi.org/10.30737/jurmateks.v5i1.2843

Keywords:

Critical Path, PERT, Project Management, Scheduling

Abstract

Project scheduling is one of the important factors for successful project implementation that can be achieved in accordance with the initial planning. Problems that can hinder project management are limited resources, inaccurate reports and costly and costly.  The delay in the completion of the project itself is a very undesirable condition, because it can harm both parties both in terms of time or cost.  The purpose of this study is to determine the probability of accelerating the implementation time from the period obtained by taking into account the critical path and calculation of cost crashing in the Aisyiyah Ponorogo Hospital construction project.   The research method used in this study was to analyze the time schedule in the RAB by comparing the project schedule using the PERT (Program Evaluation and Review Technique) method. The data used is the duration of the project time to obtain critical trajectory results, standards and variances. The results of the scheduling analysis with the PERT method obtained a critical path with B-C-D-E-L-M with an acceleration of the implementation time of project activities for 49 weeks on the critical path and a non-critical path for 79 weeks from the planned time.  buildings can speed up implementation time by a possible percentage of 92,073% with efficient calculation of crashing costs with the addition of working hours/overtime at a duration of 49 weeks rather than having to increase labor to achieve this probability.

References

T. N. Amin, A. Ridwan, and Y. Cahyo, “Analisa Penjadwalan Dengan Metode PERT dan MATHCAD (Study Kasus Proyek Pembangunan Restaurant Farm House di Lembang),†J. Manaj. Teknol. Tek. Sipil, vol. 3, no. 1, p. 98, 2020, doi: 10.30737/jurmateks.v3i1.895.

A. S. Kembuan, R. J. M. Mandagi, and S. S. Lumeno, “Model Risiko Pengelolaan SDM Konstruksi dalam International Joint Operation pada Proyek Infrastruktur Jalan Tol Manado-Bitung,†J. Sipil Statik, vol. 7, no. 1, pp. 113–126, 2019.

N. M. Astari et al., “Perencanaan Manajemen Proyek dengan Metode CPM (Critical Path Method ) dan PERT (Program Evaluation and Review Technique),†J. Konstr., vol. 13, no. 1, pp. 164–180, 2021.

H. Langlang, B. Putra, and M. R. A. Simanjuntak, “Kajian Faktor-Faktor Pengendalian Waktu Pada Bangunan Gedung Bertingkat Di Proyek Kampus Universitas Islam Internasional Indonesia,†no. 2005, pp. 255–261, 2021.

I. S. Eva Dewi Yudsiana, “Penerapan Metode PERT dan CPM dalam Pelaksanaan Proyek Pembangunan Jalan Paving untuk Mencapai Efektivitas Waktu Penyelesaian Proyek,†J. Manaj. dan Bisnis, vol. 2, no. 3, p. 75383, 2018.

Z. Gašparíková and B. Leitner, “Application of the PERT Method in Planning of Area Evacuation of Persons,†Transp. Res. Procedia, vol. 55, pp. 1547–1554, 2021, doi: 10.1016/j.trpro.2021.07.144.

J. Harmawanto, Y. C. S. P, S. Winarto, F. Teknik, and U. Kadiri, “Analisa Anggaran Biaya dan Penjadwalan Proyek Perbaikan Tanggul Kali Bakung Desa Cengkok Kecamatan Tarokan Kabupaten Kediri,†J. Manaj. Teknol. Tek. Sipil, vol. 2, no. 2, pp. 224–235, 2019.

Y. K. Mittal, V. K. Paul, A. Rostami, M. Riley, and A. Sawhney, “Delay factors in construction of healthcare infrastructure projects: a comparison amongst developing countries,†Asian J. Civ. Eng., vol. 21, no. 4, pp. 649–661, 2020, doi: 10.1007/s42107-020-00227-1.

B. Zakariyya, A. Ridwan, and S. Suwarno, “Analisis Biaya Dan Jadwal Proyek Pembangunan Gedung Dinas Kesehatan Kabupaten Trenggalek Dengan Metode Earned Value,†J. Manaj. Teknol. Tek. Sipil, vol. 3, no. 2, p. 362, 2020, doi: 10.30737/jurmateks.v3i2.1197.

J. Harmawanto, Y. C. Setianto Poernomo, and S. Winarto, “Analisa Anggaran Biaya Danpenjadwalanproyek Perbaikan Tanggul Kali Bakungdesa Cengkok Kecamatan Tarokan Kabupaten Kediri,†J. Manaj. Teknol. Tek. Sipil, vol. 2, no. 2, p. 224, 2019, doi: 10.30737/jurmateks.v2i2.514.

J. G. Runtuwarouw, D. R. . Walangitan, and P. Pratasis, “Analisis Penerapan Manajemen Waktu Pada Proyek Pembangunan Gedung Pendidikan Fpik Universitas Sam Ratulangi Kota Manado,†J. Sipil Statik, vol. 7, no. 12, pp. 1617–1624, 2019.

F. Y. Umbara and M. Abduh, “Analisis Keterlambatan Proyek Pasar Besar Ngawi Menggunakan Metode CPM (Critical Path Method),†Pros. Semin. Nas. Teknol. dan Rekayasa 2020, pp. 7–14, 2020.

A. Angelin and S. Ariyanti, “Analisis Penjadwalan Proyek New Product Development Menggunakan Metode Pert Dan Cpm,†J. Ilm. Tek. Ind., vol. 6, no. 1, pp. 63–70, 2019, doi: 10.24912/jitiuntar.v6i1.3025.

H. C. Lee, E. B. Lee, and D. Alleman, “Schedule modeling to estimate typical construction durations and areas of risk for 1000 MW ultra-critical coal-fired power plants,†Energies, vol. 11, no. 10, 2018, doi: 10.3390/en11102850.

P. Ballesteros-Pérez, A. Cerezo-Narváez, M. Otero-Mateo, A. Pastor-Fernández, J. Zhang, and M. Vanhoucke, “Forecasting the project duration average and standard deviation from deterministic schedule information,†Appl. Sci., vol. 10, no. 2, 2020, doi: 10.3390/app10020654.

L. Malyusz, M. Hajdu, and Z. Vattai, “Comparison of different algorithms for time analysis for CPM schedule networks,†Autom. Constr., vol. 127, p. 103697, 2021, doi: 10.1016/j.autcon.2021.103697.

D. C. Setiawan, A. Ridwan, and S. Suwarno, “Optimalisasi Penjadwalan Proyek Pembangunan Gedung Puskesmas Badas Menggunakan Critical Path Method-Project Evaluation and Review Technique (CPM-PERT),†J. Manaj. Teknol. Tek. Sipil, vol. 4, no. 2, p. 71, 2021, doi: 10.30737/jurmateks.v4i2.2011.

T. Iluk, A. Ridwan, and S. Winarto, “Penerapan Metode CPM Dan PERT Pada Gedung Parkir 3 Lantai Grand Panglima Polim Kediri,†J. Manaj. Teknol. Tek. Sipil, vol. 3, no. 2, p. 162, 2020, doi: 10.30737/jurmateks.v3i2.1054.

F. Muhammad Azhari, A. Iwan Candra, D. Aprillia Karisma, A. Yamin, and F. Rahmawaty, “Accelerate the Implementation Time of Kadiri University Clinic Constructions Projects Using Critical Path Method (CPM),†E3S Web Conf., vol. 328, p. 10001, 2021, doi: 10.1051/e3sconf/202132810001.

Z. A. Collier, D. Hendrickson, T. L. Polmateer, and J. H. Lambert, “Scenario Analysis and PERT/CPM Applied to Strategic Investment at an Automated Container Port,†ASCE-ASME J. Risk Uncertain. Eng. Syst. Part A Civ. Eng., vol. 4, no. 3, 2018, doi: 10.1061/ajrua6.0000976.

S. Abbasi, K. Taghizade, and E. Noorzai, “BIM-Based Combination of Takt Time and Discrete Event Simulation for Implementing Just in Time in Construction Scheduling under Constraints,†J. Constr. Eng. Manag., vol. 146, no. 12, 2020, doi: 10.1061/(asce)co.1943-7862.0001940.

S. Ahmed and A. F. Mohammed, “From process flows to benchmark in an accident and emergency hospital with PERT approach,†Kybernetes, vol. 48, no. 3, pp. 520–545, 2019, doi: 10.1108/K-02-2018-0088.

H. K. Chang, W. der Yu, S. T. Cheng, and T. M. Cheng, “The Use of a Multiple Risk Level Model to Tackle the Duration of Risk for Construction Activity,†KSCE J. Civ. Eng., vol. 23, no. 6, pp. 2397–2408, 2019, doi: 10.1007/s12205-019-1757-8.

M. R. Hermawan, A. Ridwan, and S. Suwarno, “Mengurangi Durasi Pelaksanaan Proyek Dengan Menggunakan Metode Time Cost Trade Off,†J. Manaj. Teknol. Tek. Sipil, vol. 4, no. 2, p. 13, 2021, doi: 10.30737/jurmateks.v4i2.1829.

A. P. Putra, E. N. Cahya, and J. Sidqi, “Studi Manajemen Proyek Rehabilitasi Daerah Irigasi Domas Kabupaten Pasuruan Menggunakan Metode Crashing dan Fasttrack,†vol. 2, no. 2, pp. 222–233, 2022.

F. Fakhrmoosavi and K. Abdelghany, “An iterative learning approach for network contraction : Path finding problem in stochastic time-varying networks,†pp. 1–18, 2019, doi: 10.1111/mice.12460.

PlumX Metrics

Published

2022-07-19

Issue

Section

Articles