PELAKSANAAN MANAJEMEN KONSTRUKSI PADA PROYEK PEMBANGUNAN BANK SINAR MAS KEDIRI
DOI:
https://doi.org/10.30737/ukarst.v2i1.101Abstract
Â
Bank Sinar Mas Kediri project is a development project that uses a unique implementation method, namely the Top Down method, that is, the construction starts from the floor plate as a new foundation and then continues with the construction of the ground floor 1,2,3. The use of the Top Down method requires a column called King Post which is a column of steel profiles as a temporary column. The hotel is built on a land area of 3248 m2 with a building height of + 123,600 m, - 9,800 m and uses 118 boredpile foundations. This project uses the Fixed Price Lumpsum contract system. This research aims to identify the cause of the delay in the completion of the Sinar Mas Kediri development project. The results of the analysis show that the delay in the completion of the project is due to the delay in completion of the excavation work. The delay was due to the lack of procurement of water pumping or drying equipment, weather or climate and the lack of excavation and limited number of heavy equipment used.
Â
Keywords: Delays, Time, Construction.
Â
Â
Proyek Bank Sinar Mas Kediri merupakan proyek pembangunan yang menggunakan metode pelaksanaan yang unik yaitu metode Top Down yaitu pembangunan dimulai dari pelat lantai sebagai tumpuan baru kemudian dilanjutkan dengan pembangunan lantai dasar 1,2,3. Penggunaan metode Top Down memerlukan kolom yang disebut King Post yang merupakan kolom dari profil baja sebagai kolom sementara. Hotel tersebut dibangun di atas tanah seluas 3248 m2 dengan tinggi bangunan + 123,600 m, - 9,800 m dan menggunakan 118 pondasi boredpile. Proyek ini menggunkan sistem kontrak Lumpsum Fixed Price.Penelitian ini bertujuan untuk mengidentifikasi penyebab keterlambatan penyelesaian proyek pembangunan Bank Sinar Mas Kediri. Hasil analisis menunjukkan bahwa Keterlambatan penyelesaian proyek disebabkan keterlambatan penyelesaian pekerjaan penggalian tanah. Keterlambatan tersebut dikarenakan kurangnya pengadaan akan alat pemompa air atau alat pengeringan, cuaca atau iklim dan tidak adanya jumlah tenaga kerja penggalian dan terbatasnya jumlah alat berat yang digunakan.
Â
Kata Kunci : Keterlambatan, Waktu, Konstruksi
Â
Kata Kunci : keterlambatan, waktu, konstruksi.
References
Frederika, A. (2010). Analisis percepatan pelaksanaan dengan menambah jam kerja optimum pada proyek konstruksi (Studi kasus: Proyek pembangunan super villa, Peti Tenget-Badung). Jurnal Ilmiah Teknik Sipil.
Tuelah, J. D. P., Tjakra, J., & Walangitan, D. R. O. (2014). PERANAN KONSULTAN MANAJEMEN KONSTRUKSI PADA TAHAP PELAKSANAAN PROYEK PEMBANGUNAN (Studi Kasus: THE LAGOON TAMAN SARI). TEKNO, 12(61).
Iwawo, E. R., Tjakra, J., & Pratasis, P. A. (2016). Penerapan metode cpm pada proyek konstruksi (studi kasus pembangunan gedung baru kompleks eben haezar manado). Jurnal Sipil Statik, 4(9).
Kani, B. R., Mandagi, R. J., p Rantung, J., & Malingkas, G. Y. (2013). Keselamatan dan Kesehatan Kerja pada Pelaksanaan Proyek Konstruksi (Studi Kasus: Proyek PT. Trakindo Utama). Jurnal Sipil Statik, 1(6).
Pangkey, F., Malingkas, G. Y., & Walangitan, D. R. O. (2012). Penerapan Sistem Manajemen Keselamatan dan Kesehatan Kerja (SMK3) Pada Proyek Konstruksi di Indonesia (Studi Kasus: Pembangunan Jembatan Dr. Ir. Soekarno-Manado). Jurnal Ilmiah Media Engineering, 2(2).
Maromi, M. I., & Indryani, R. (2015). Metode Earned Value untuk Analisa Kinerja Biaya dan Waktu Pelaksanaan pada Proyek Pembangunan Condotel De Vasa Surabaya. Jurnal Teknik ITS, 4(1), D54-D59.
Hastuti, S. P. (2014). Waste Management Pada Proyek Pembangunan Gedung Sebagai Bagian Dari Upaya Perwujudan Green Construction (Studi Kasus: Pembangunan Gedung–Gedung Di Universitas Sebelas Maret Surakarta).
Tolangi, M. F., Rantung, J. P., Langi, J. E. C., & Sibi, M. (2012). Analisis Cash Flow Optimal Pada Kontraktor Proyek Pembangunan Perumahan. Jurnal Sipil Statik, 1(1).
Kani, B. R., Mandagi, R. J., p Rantung, J., & Malingkas, G. Y. (2013). Keselamatan dan Kesehatan Kerja pada Pelaksanaan Proyek Konstruksi (Studi Kasus: Proyek PT. Trakindo Utama). Jurnal Sipil Statik, 1(6).
Tarore, H., Malingkas, G. Y., & Walangitan, D. R. (2012). Pengendalian Waktu dan Biaya Pada Tahap Pelaksanaan Proyek dengan Menggunakan Metode Nilai Hasil (Studi Kasus: Proyek Lanjutan Pembangunan Gedung PIP2B Kota Manado). Jurnal Sipil Statik, 1(1).
S. Aminah, “Konflik dan Kontestasi Penataan Ruang Kota Surabaya,†Masy. J. Sosiol., vol. 20, no. 1, pp. 59–79, 2016.
P. Vitasmoro, A. I. Chandra, and J. Jatmiko, “Improving Student ’ s English Vocabulary Mastery through Animation Cartoon,†vol. 363, no. Icss, pp. 505–509, 2019.
A. Meylani and A. S. Handayani, “Perbandingan Kinerja Sistem Logika Fuzzy Tipe-1 dan Interval Tipe-2 pada Aplikasi Mobile Robot,†vol. 3, no. 1, pp. 209–214, 2017.
M. Irfan, L. P. Ayuningtias, and J. Jumadi, “Analisa Perbandingan Logic Fuzzy Metode Tsukamoto, Sugeno, Dan Mamdani ( Studi Kasus : Prediksi Jumlah Pendaftar Mahasiswa Baru Fakultas Sains Dan Teknologi Uin Sunan Gunung Djati Bandung),†J. Tek. Inform., vol. 10, no. 1, pp. 9–16, 2018.
U. Katolik et al., “Estimasi Parameter Bilangan Fuzzy Segitiga Untuk Model Pembebanan Lalulintas Fuzzy,†no. June, pp. 8–9, 201
Downloads
Published
How to Cite
Issue
Section
License
Authors who publish with this journal agree to the following terms:
(1) The copyright of published articles will be transferred to the journal as the publisher of the manuscript. Therefore, the author needs to confirm that the copyright has been managed by the publisher with the Publication Right Form which must be attached when submitting the article.
(2) Publisher of U Karst is Kadiri University.
(3) The copyright follows Creative Commons Attribution-ShareAlike License (CC BY SA): This license allows to Share copy and redistribute the material in any medium or format, Adapt remix, transform, and build upon the material, for any purpose, even commercially.