Perencanaan Mitigasi Risiko Berbasis Event Tree Analysis untuk Meningkatkan Keandalan PLTGU

Authors

  • Sastya Adzani Syahbania Institut Teknologi Sepuluh Nopember (ITS)
  • I Ketut Gunarta Institut Teknologi Sepuluh Nopember

DOI:

https://doi.org/10.30737/jatiunik.v9i2.6495

Keywords:

Critical Equipment, ETA, Failure Probability, Reliability Levels, Cycle Power Plants

Abstract

Repeated failures of critical equipment at power generation facilities can significantly disrupt operations and reduce system availability. In 2023, PT X's Block 1 Unit A Combined Cycle Power Plant recorded its lowest Equivalent Availability Factor (EAF) of 84.95% due to repeated failures of several critical components. Previous studies have identified these equipment failures and analyzed their reliability levels. This study aims to develop mitigation scenarios to reduce operational risks using Event Tree Analysis (ETA). ETA uses failure probabilities from previous reliability assessments as initiating events to model potential event sequences and evaluate their consequences. The results show that each tool generates between 4 and 16 scenario pathways, depending on the number of mitigation programs. All proposed mitigation scenarios successfully reduced the overall risk level to “Low” across all seven critical pieces of equipment. This study concludes that ETA provides an effective way to systematically organize mitigation efforts based on failure probability and consequence analysis. The contribution of this study is the development of a scenario-based mitigation framework using ETA to support decision-making and enhance operational reliability at combined-cycle power plants.

Author Biography

  • I Ketut Gunarta, Institut Teknologi Sepuluh Nopember

    Department of Systems and Industrial Engineering

References

[1] Adriwiyono and B. Ichtiarto, “Analisa Kinerja Pembangkit Turbin Gas PT PJB Unit Pembangkitan Muara Tawar menggunakan Generating Availability Data System,” 2018.

[2] W. N. Cahyo and N. Ardyanto, “Maintenance Management Analysis of Induce Draft Fan (IDF) Equipment of Coal Fire Power Plant (CFPP) Lontar using Life Cycle Cost Analysis Approach,” Spektrum Industri, vol. 18, no. 2, p. 145, Oct. 2020, doi: 10.12928/si.v18i2.17515.

[3] B. Wahyudi, H. B. Santoso, and S. Rahayuningsih, “Keandalan Sistem Instrumentasi dengan Metode Markov Chain,” WIT Trans. Inf. Commun. Technol, vol. 5, no. 2, pp. 1147–1157, 2022, doi: 10.30737/jatiunik.v5i2.2159.g2065.

[4] M. R. Mamdikar, V. Kumar, P. Singh, and L. Singh, “Reliability and performance analysis of safety-critical system using transformation of UML into state space models,” Ann Nucl Energy, vol. 146, Oct. 2020, doi: 10.1016/j.anucene.2020.107628.

[5] PT PLN (Persero), “Indikator Kinerja Pembangkit,” 2007.

[6] PT X, “Realisasi EAF PT X 2019–2023,” 2024.

[7] D. Choudhary, M. Tripathi, and R. Shankar, “Reliability, Availability and Maintainability Analysis of a Cement Plant: a Case Study,” International Journal of Quality and Reliability Management, vol. 36, no. 3, pp. 298–313, Mar. 2019, doi: 10.1108/IJQRM-10-2017-0215.

[8] P. Tsarouhas, “Maintenance Scheduling of a Cheddar Cheese Manufacturing Plant based on RAM Analysis,” International Journal of Productivity and Performance Management, vol. 71, no. 2, pp. 666–690, Jan. 2022, doi: 10.1108/IJPPM-01-2021-0010.

[9] F. Crawley, “Event Tree Analysis,” in A Guide to Hazard Identification Methods, Elsevier, 2020, pp. 125–130. doi: 10.1016/b978-0-12-819543-7.00014-8.

[10] N. Veljanovski and M. Čepin, “Event Tree-based Risk and Financial Assessment for Power Plants,” Reliab Eng Syst Saf, vol. 247, Jul. 2024, doi: 10.1016/j.ress.2024.110122.

[11] S. Yuan, J. Cai, G. Reniers, M. Yang, C. Chen, and J. Wu, “Safety Barrier Performance Assessment by Integrating Computational Fluid Dynamics and Evacuation Modeling for Toxic Gas Leakage Scenarios,” Reliab Eng Syst Saf, vol. 226, Oct. 2022, doi: 10.1016/j.ress.2022.108719.

[12] M. P. Brito and I. G. J. Dawson, “Predicting the Validity of Expert Judgments in Assessing the Impact of Risk Mitigation Through Failure Prevention and Correction,” Risk Analysis, vol. 40, no. 10, pp. 1928–1943, Oct. 2020, doi: 10.1111/risa.13539.

[13] E. Kurniawan, W. Gunawan, and A. Syarifudin, “Analisa Vibrasi Main Sea Water Pump Dengan Metode Overall Equipment Effectiveness Dan Failure Modes And Effect Analysis Di Pt Krakatau Daya Listrik,” JOURNAL INDUSTRIAL ENGINEERING & MANAGEMENT RESEARCH ( JIEMAR), vol. 1, no. 2, pp. 2722–8878, 2020, doi: 10.7777/jiemar.v1i2.

[14] I. Q. Saffar and A. W. Ezzat, “Probabilistic Risk Assessment of Typical Process Plant Using Event Tree and Fault Tree Analysis,” Journal of Mechanical Engineering Research and Developments, vol. 43, no. 7, pp. 465–477, 2020, [Online]. Available: https://www.researchgate.net/publication/346955478

[15] Z. Zafirovski, V. Gacevski, Z. Krakutovski, and S. Ognjenovic, “Methodology for Tunnel Risk Assessment using Fault and Tree Analysis,” 2021, doi: 10.5592/CO/CETRA.2020.

[16] S. C. Gulen, Gas Turbine Combined Cycle Power Plants. Taylor & Francis Group, 2020.

[17] R. Lesmana, “Analisis Kinerja Unit Pembangkit Akibat Outage Berdasarkan Equivalent Availability Factor dan Net Capacity Factor di PLTA Lamajan Pangalengan,” 2023.

[18] John. Lark and Valentin. Nikonov, ISO31000 Risk Management: a Practical Guide for SMEs. International Organization for Standardization : International Trade Centre : UNIDO, 2015.

[19] C. L. Pritchard, Risk Management: Concepts and Guidance, Fifth Edition. 2015.

[20] J. D. Andrews and T. R. Moss, Reliability and Risk Assessment, Second edition. Professional Engineering Publishing, 2002.

[21] A. Birolini, Reliability Engineering: Theory and Practice. Berlin, Heidelberg: Springer Berlin Heidelberg, 2017. doi: 10.1007/978-3-662-54209-5.

[22] R. F. Stapelberg, Handbook of Reliability, Availability, Maintainability and Safety in Engineering Design. Springer London, 2009. doi: 10.1007/978-1-84800-175-6.

[23] V. de Vasconcelos, W. Antonio Soares, A. Carlos Lopes da Costa, and A. Laureano Raso, “Treatment of Uncertainties in Probabilistic Risk Assessment,” in Reliability and Maintenance - An Overview of Cases, IntechOpen, 2020. doi: 10.5772/intechopen.83541.

Downloads

Published

2026-02-18

Issue

Section

Articles

Deprecated: json_decode(): Passing null to parameter #1 ($json) of type string is deprecated in /home/ojs.unik-kediri.ac.id/public_html/plugins/generic/citations/CitationsPlugin.php on line 68

How to Cite

Perencanaan Mitigasi Risiko Berbasis Event Tree Analysis untuk Meningkatkan Keandalan PLTGU. (2026). JATI UNIK : Jurnal Ilmiah Teknik Dan Manajemen Industri, 9(2), 14-24. https://doi.org/10.30737/jatiunik.v9i2.6495

Similar Articles

11-20 of 37

You may also start an advanced similarity search for this article.