Meminimalisir Keterlambatan Waktu dan Pembengkakan Biaya Proyek Pembangunan Gedung Kecamatan Dongko, Trenggalek dengan Metode Nilai Hasil (Earned Value Method)

Authors

  • Mohammad Bismo Febriantoro Faculty of Engineering, Kadiri University
  • Sony Susanto Faculty of Engineering, Kadiri University
  • Eko Siswanto Faculty of Engineering, Kadiri University

DOI:

https://doi.org/10.30737/jurmateks.v5i1.2881

Keywords:

ACWP, BCWP, BCWS, Budget, Earned Value Method, Performance and Time

Abstract

The construction of the Dongko Trenggalek District Building is one of the Trenggalek government's work programs in an effort to improve the quality of community services. In the construction of a building, proper project management needs to be done to minimize the occurrence of project failures. This study aims to minimize delays and cost overruns in the Dongko District Building Project, Trenggalek. Efforts to control the project are carried out with the result value method. EVM is one of the methods used to measure and evaluate the progress and performance of a project The result value method is applied by performing performance analysis which includes cost and schedule analysis, variance analysis, performance index analysis and cost estimation analysis and work end time. The project was built with a contract value of Rp. 2,902,468,0000.00 and is planned to be completed within 154 days. The results showed that the project experienced delays from what was planned. The completion time was delayed from the planned time from 154 days to 170 days with a total project cost of Rp. 2,932,467,150 which indicates that the budgeted costs for the work carried out experienced overhead or cost overruns. By knowing this, the implementer can evaluate the work early so as to minimize the occurrence of project failure.

References

E. Y. A. Rumere, J. Tjakra, and R. L. Ingkiriwang, “Konsep Nilai Hasil Terhadap Waktu Dan Biaya Pada Pekerjaan Proyek Pembangunan Rumah Postulat Ursulin Ende Nusa Tenggara Timur,†Tekno, vol. 17, no. 73, pp. 105–113, 2019.

P. Ballesteros-Pérez, E. Sanz-Ablanedo, D. Mora-Melià , M. C. González-Cruz, J. L. Fuentes-Bargues, and E. Pellicer, “Earned Schedule min-max: Two new EVM metrics for monitoring and controlling projects,†Autom. Constr., vol. 103, no. November 2018, pp. 279–290, 2019, doi: 10.1016/j.autcon.2019.03.016.

C. J. Van Wyngaard, J. H. C. Pretorius, and L. Pretorius, “Theory of the triple constraint -A conceptual review,†IEEE Int. Conf. Ind. Eng. Eng. Manag., no. December 2019, pp. 1991–1997, 2012, doi: 10.1109/IEEM.2012.6838095.

I. A. P. S. Mahapatni, I. B. Wirahaji, and I. M. H. Wijaya, “Pengendalian Proyek dengan Earned Value Method (Evm) pada Proyek Pemeliharaan Jalan Provinsi Denpasar- Simpang Pesanggaran,†Widya Tek., vol. 13, no. 02, pp. 37–46, 2019, doi: 10.32795/widyateknik.v13i02.508.

A. Mishakova, A. Vakhrushkina, V. Murgul, and T. Sazonova, “Project Control Based on a Mutual Application of Pert and Earned Value Management Methods,†Procedia Eng., vol. 165, pp. 1812–1817, 2016, doi: 10.1016/j.proeng.2016.11.927.

D. D. Putra, N. Paryati, and E. Yulius, “Faktor Keterlambatan Pekerjaan Struktur Gedung terhadap Biaya Pelaksanaan pada Proyek Pembangunan Hotel di Bekasi,†Bentang J. Teor. dan Terap. Bid. Rekayasa Sipil, vol. 7, no. 2, pp. 110–119, 2019, doi: 10.33558/bentang.v7i2.1752.

N. Sa’adah, E. Iqrammah, and T. Rijanto, “Evaluasi Proyek Pembangunan Gedung Stroke Center (Paviliun Flamboyan) Menggunakan Metode Critical Path Method (CPM) Dan Crashing,†Publ. Ris. Orientasi Tek. Sipil, vol. 3, no. 2, pp. 55–62, 2022, doi: 10.26740/proteksi.v3n2.p55-62.

P. A. K.Pratasis and G. Malingkas, “Analisis Metode Nilai Hasil Terhadap Waktu Dan Biaya Pada Proyek Office and Distribution Center, Airmadidi, Minahasa Utara-Manado.,†J. Sipil Statik, vol. 7, no. 11, pp. 1453–1476, 2019.

E. P. Sukmono, Z. Zainuri, and W. Apriani, “Pengendalian Biaya dan Waktu dengan Metode Earned Value (Studi Kasus : Rancang dan Bangun Sistem Penyediaan Air Minum Kota Dumai 450 LPD Tahap 1A),†J. Rekayasa Konstr. Mek. Sipil, vol. 04, no. 2, pp. 45–54, 2021, doi: 10.54367/jrkms.v4i1.1124.

J. V. B. Ginting, “Metode Earned Value pada Pengendalian Proyek Pembangunan Gedung Sekolah SD Methodist-an Pancur Batu,†Arbitr. J. Econ. Account., vol. 1, no. 1, pp. 6–10, 2020.

N. Khairunnisa, R. Widayati, and M. Jamal, “Analisis Pengendalian Biaya dan Waktu Terhadap Proyek Konstruksi Dengan Metode Earned Value (Studi Kasus: Proyek Perumahan Penajam Paser Utara),†J. Teknol. Sipil, vol. 4, no. 1, pp. 9–19, 2020.

W. I. Ervianto, Manajemen Proyek Konstruksi, Edisi Pertama. 2002.

M. D. Sruthi and A. Aravindan, “Performance measurement of schedule and cost analysis by using earned value management for a residential building,†Mater. Today Proc., vol. 33, no. xxxx, pp. 524–532, 2020, doi: 10.1016/j.matpr.2020.05.210.

B. Zohoori, A. Verbraeck, M. Bagherpour, and M. Khakdaman, “Monitoring production time and cost performance by combining earned value analysis and adaptive fuzzy control,†Comput. Ind. Eng., vol. 127, pp. 805–821, 2019, doi: 10.1016/j.cie.2018.11.019.

A. Purnomo et al., “Pengendalian Biaya dan Waktu Proyek Gedung SMK Dwija Bhakti Jombang Dengan Menggunakan Metode Earned Value,†Tecnoscienza, vol. 4, no. 1, pp. 40–52, 2019.

N. I. Hayati and D. Lugi, “EVALUASI BIAYA DAN WAKTU DENGAN METODE EARNED VALUE MANAGEMENT (Studi Kasus: Ruko Damara Village, Kel. Ciparigi, Kota Bogor),†J. Komposit, vol. 4, no. 2, p. 61, 2022, doi: 10.32832/komposit.v4i2.3760.

A. Abdi, S. Taghipour, and H. Khamooshi, “Corrigendum to ‘A model to control environmental performance of project execution process based on greenhouse gas emissions using earned value management’ (International Journal of Project Management (2018) 36(3) (397–413), (S0263786317308001) (10.1016/j.,†Int. J. Proj. Manag., vol. 36, no. 8, pp. 1047–1049, 2018, doi: 10.1016/j.ijproman.2018.07.006.

F. Ariane and D. Dinariana, “Earned Value Analysis Pada Pengendalian Waktu Proyek Venue Layar Di Dki Jakarta,†J. IKRA-ITH Teknol., vol. 2, no. 3, pp. 51–54, 2018.

R. Votto, L. Lee Ho, and F. Berssaneti, “Multivariate control charts using earned value and earned duration management observations to monitor project performance,†Comput. Ind. Eng., vol. 148, no. July, p. 106691, 2020, doi: 10.1016/j.cie.2020.106691.

Y. W. Nufah, G. Yanti, and F. Lubis, “Analisis Proyek Dengan Metode Earned Value Concept (Studi Kasus Pada Proyek Pembangunan Jalan Tol Ruas Pekanbaru – Dumai Seksi 2 STA. 9+500 - 33+600),†Semin. Nas. Cendekiawan ke 5 Tahun 2019 Buku 1 â€Teknologi dan Sains“, vol. 1, pp. 1–7, 2019.

J. Song, A. Martens, and M. Vanhoucke, “Using Earned Value Management and Schedule Risk Analysis with resource constraints for project control,†Eur. J. Oper. Res., vol. 297, no. 2, pp. 451–466, 2022, doi: 10.1016/j.ejor.2021.05.036.

B. Susanti, M. Melisah, and I. Juliantina, “Penerapan Konsep Earned Value Pada Proyek Konstruksi Jalan Tol (Studi Kasus Ruas Jalan Tol Kayuagung - Palembang -Betung),†J. Rekayasa Sipil, vol. 15, no. 1, p. 12, 2019, doi: 10.25077/jrs.15.1.12-20.2019.

B. Zakariyya, A. Ridwan, and S. Suwarno, “Analisis Biaya Dan Jadwal Proyek Pembangunan Gedung Dinas Kesehatan Kabupaten Trenggalek Dengan Metode Earned Value,†J. Manaj. Teknol. Tek. Sipil, vol. 3, no. 2, p. 362, 2020, doi: 10.30737/jurmateks.v3i2.1197.

et al., “Analisis dan Evaluasi Kinerja Proyek Pembangunan Gedung Shelter SDN 27 Lengayang Pesisir Selatan dengan Metode Earned Value,†J. Tek. Sipil ITP, vol. 6, no. 2, pp. 71–77, 2019, doi: 10.21063/jts.2019.v602.05.

D. Bryde, C. Unterhitzenberger, and R. Joby, “Conditions of success for earned value analysis in projects,†Int. J. Proj. Manag., vol. 36, no. 3, pp. 474–484, 2018, doi: 10.1016/j.ijproman.2017.12.002.

PlumX Metrics

Published

2022-07-19

Issue

Section

Articles