ANALISA PENJADWALAN DENGAN METODE PERT DAN MATHCAD (Study Kasus Proyek Pembangunan Restaurant Farm House di Lembang)

Authors

  • Tofek Nur' Amin Fakultas Teknik Universitas Kadiri
  • Ahmad Ridwan Fakultas Teknik Universitas Kadiri
  • Yosef Cahyo Fakultas Teknik Universitas Kadiri

DOI:

https://doi.org/10.30737/jurmateks.v3i1.895

Keywords:

PERT, MathCad, Scheduling Analysis, Optimum Analysis

Abstract

Project control is one of the functions and processes in project management that influences the project's outcome. Project control has an essential role in minimizing any deviations that can occur during the project process. In project scheduling, need to, management planning, schedule, and control. Development of Restaurant Farm House planned by PT. DWI MARTHA JAYA is estimated to take 334 days at the cost of Rp. 9.068.780.000,00. Based on information obtained in the field. The type of research method applied in this research is the schedule analysis method on the RAB (Budget Plan) by comparing and analyzing project scheduling using PERT and MathCad methods. The data collection techniques chosen were observation and documentary. From the results of the analysis, the completion time of the Restaurant Farm House construction project is 310 days and a labor cost savings of Rp. 93,341,832.00 out of a total cost of Rp 9.068.780.000,00. So that an overall loss of Rp 8.975.438.168,00.

 

Pengendalian proyek merupakan salah satu fungsi dan proses dalam manajemen proyek yang berpengaruh pada hasil akhir proyek. Pengendalian proyek mempunyai peran penting dalam meminimalisasi segala penyimpangan yang dapat terjadi selama proses berlangsungnya proyek. Pada penjadwalan proyek diperlukan penanganan manajemen kerja yang terdiri dari perencanaan, penjadwalan dan pengendalian. Pembangunan Restaurant Farm House yang direncanakan oleh PT. DWI MARTHA JAYA diperkirakan memakan waktu 334 hari dengan biaya Rp. 9.068.780.000,00. Hal ini berdasarkan informasi yang diperoleh di lapangan. Jenis metode penelitian yang diterapkan dalam penelitian ini adalah metode analisis time schedule pada RAB (Rencana Anggaran Biaya) dengan membandingkan dan melakukan analisa penjadwalan proyek menggunakan metode PERT dan MathCad. Teknik pengumpulan data yang dipilih adalah dengan observasi dan dokumenter. Dari hasil analisis dengan dua metode tersebut diperoleh waktu penyelesaian proyek pembangunan Restaurant Farm House adalah 310 hari dan diperoleh penghematan biaya tenaga kerja sebesar Rp. 93.341.832,00 dari biaya total Rp 9.068.780.000,00, sehingga diperoleh biaya keseluruhan Rp 8.975.438.168,00.

 

References

D. M. Walean, R. J. M. Mandagi, J. Tjakra, and G. Y. Malingkas, “Perencanaan dan Pengendalian Jadwal Dengan Menggunakan Program Microsoft Project 2010 (Studi Kasus: Proyek PT. Trakindo Utama),†J. Sipil Statik, vol. 1, no. 1, pp. 22–26, 2012.

J. Harmawanto, Y. C. S. P, and S. Winarto, “ANALISA ANGGARAN BIAYA DAN PENJADWALAN PROYEK PERBAIKAN TANGGUL KALI BAKUNG DESA CENGKOK KECAMATAN TAROKAN KABUPATEN KEDIRI,†Jurmateks, vol. 2, no. 2, pp. 224–235, 2019.

A. H. A, “Perencanaan dan Pengendalian Proyek dengan Metode Pert - CPM Studi Kasus : Fly Over Ahmad Yani – Karawang,†The Winners, vol. 6, no. 2, p. 155, 2005, doi: 10.21512/tw.v6i2.605.

A. Ridwan, “PENGENDALIAN BIAYA DAN JADUAL TERPADU PADA PROYEK KONSTRUKSI,†vol. 1, no. 1, pp. 74–83, 2017.

A. I. Candra et al., “PENGECEKAN KELAYAKAN BANGUNAN GEDUNG SMA NEGERI 1 KOTA KEDIRI YANG DIGUNAKAN UNTUK AKTIFITAS BELAJAR BELAJAR,†Ukarst J. Univ. Kadiri Ris. Tek. Sipil, vol. 2, no. 2, pp. 108–116, 2019.

A. Lokobal, M. Sumajouw, and B. Sompie, “Manajemen Risiko Pada Perusahaan Jasa Pelaksana Konstruksi Di Propinsi Papua (Study Kasus Di Kabupaten Sarmi),†J. Ilm. Media Eng., vol. 4, no. 2, p. 100881, 2014.

A. H. P. Rantung, B. F. Sompie, and R. J. M. Mandagi, “Analisis Pengendalian Biaya Dan Jadwal Pada Tahap Pelaksanaan Konstruksi Dengan ‘Analisis Nilai Hasil’ (Earned Value Analysis),†J. Ilm. Media Eng. Tek. Sipil Univ. Sam Ratulangi Manad., vol. 4, no. 3, pp. 190–203, 2014.

M. Kareth, H. Tarore, J. Tjakra, and D. R. O. Walangitan, “ANALISIS OPTIMALISASI WAKTU DAN BIAYA DENGAN PROGRAM PRIMAVERA 6.0 (Studi Kasus : Proyek Perumahan Puri Kelapa Gading),†J. Sipil Statik, vol. 1, no. 1, pp. 53–59, 2012.

R. Hidayah, A. Ridwan, and Y. C. S. P, “ANALISA PERBANDINGAN MANAJEMEN WAKTU ANTARA PERENCANAAN DAN PELAKSANAAN,†Jurmateks, vol. 1, no. 2, pp. 281–290, 2018.

A. D. Limantara, A. I. Candra, and S. W. Mudjanarko, “MANAJEMEN DATA LALU LINTAS KENDARAAN BERBASIS SISTEM INTERNET CERDAS KADIRI,†semnastek, no. November, pp. 1–2, 2017.

T. A. Bria and O. Loden, “Manajemen Risiko Keselamatan Dan Kesehatan Kerja (K3) Pada Proyek- Proyek Konstruksi Di Kota Kupang,†JUTEKS - J. Tek. Sipil, vol. 1, no. 2, p. 96, 2017, doi: 10.32511/juteks.v1i2.113.

R. H. Irawan Agustiar, “EVALUASI PENJADWALAN PROYEK MENGGUNAKAN METODE CPM DAN KURVA S (Studi,†vol. 07, no. 02, pp. 99–105, 2018.

M. N. Ihwanudin, “Analisa Penjadwalan Proyek Pipa Carbon Dengan Metode Fuzzy Logic Application for Scheduling,†Stat. F. Theor, vol. 53, no. 9, pp. 1689–1699, 2017.

A. I. Candra, A. Yusuf, and A. R. F, “Studi Analisis Daya Dukung Pondasi Tiang Pada Pembangunan Gedung Lp3M Universitas Kadiri,†J. CIVILA, vol. 3, no. 2, p. 166, 2018, doi: 10.30736/cvl.v3i2.259.

F. Astutik, “Artikel Skripsi Universitas Nusantara PGRI Kediri ANALISIS PENERAPAN METODE,†Ekon. Akunt., vol. 01, no. 08, pp. 1–13, 2016.

G. Y. Malingkas, T. T. Arsjad, and H. Tarore, “Menganalisis Sensitivitas Keterlambatan Durasi,†vol. 1, no. 9, pp. 603–607, 2013.

S. M. Khoiroh, “Mengoptimalkan Crashing Project Pemasangan Saluran Rumah Di Perumahan X Dengan Pendekatan Cpm-Pert,†vol. 15, no. 1, pp. 39–48, 2018.

I. Raharja, “Analisa Penjadwalan Proyek Dengan Metode Pert Di Pt. Hasana Damai Putra Yogyakarta Pada Proyek Perumahan Tirta Sani,†Bentang, vol. 2, no. 1, p. 262530, 2014.

H. R. Agustapraja and D. Kartikasari, “Studi Evaluasi Pekerjaan Struktur Box Culvert Pada Proyek Pembangunan Jembatan Kucing Ruas Sukodadi – Sumberwudi Kabupaten Lamongan,†UKaRsT, vol. 1, no. 1, pp. 45–54, 2017, doi: 10.30737/ukarst.v1i1.261.

Y. C. S. Poernomo, A. Ridwan, Z. Lubis, A. Gunarto, and S. Winarto, “Pelaksanaan Manajemen Konstruksi Pada Proyek Pembangunan Bank Sinar Mas Kediri,†UKaRsT, vol. 2, no. 1, p. 52, 2018, doi: 10.30737/ukarst.v2i1.101.

J. M. Boyer and S. C. Chapra, “RECOVERY , A Mathematical Model to Predict the Temporal Response of Surface Water to Contaminated Sediments,†Engineer, vol. 94, no. 4, pp. 2–89, 1994.

C. Witriyatna, A. Purnomo, Dwi, B. W, Agung, and M. Marinda, “Analisis Perbandingan Modul Jembatan Gelagar I Sebagai Fungsi Jembatan Jalan Raya Comparison Analysis of I Girder Bridge Module and Steel Box Girder As a Function of Road Bridge,†vol. 12, no. 2, pp. 115–126, 2016.

E. Mahudi, Y. C. S. P, and A. Ridwan, “STUDI ANALISA DAMPAK LALU LINTAS DIKAWASAN PEMBANGUNAN GEDUNG OLAH RAGA KABUPATEN TRENGGALEK,†Jurmateks, vol. 2, no. 2, pp. 203–213, 2019.

Downloads

PlumX Metrics

Published

2020-06-30

Issue

Section

Articles