COST PERFORMANCE ANALYSIS AND TIME DEVELOPMENT CONSTRUCTION PROJECT BRIDGE CHAIN KARANGGENENG NAWACITA CS USING THE EARNED VALUE METHOD

Authors

  • Bobby Damara Faculty of Engineering, Islamic Of University Lamongan

DOI:

https://doi.org/10.30737/ukarst.v4i2.1067

Keywords:

Time, Cost, Earned Value, Method

Abstract

Cost, quality, and time are mandatory targets of construction management; project work can be said to be successful if triple constants cost, quality, and time the construction work of the Karanggeneng Nawacita Cs Suspension Bridge is a JUDESA project APBN project and has a period of 19 weeks working days with a budget of Rp 8.213.826.000, in the process of implementing the bridge construction, it is not free from several technical and non-technical constraints, the method earned value in this study used to determine Early Warning and integrate the concept of time and cost from the method, it earned value can be seen the progress and performance of the project with SV, CV, SPI, CPI, ECD, and EAC, from this study the results obtained ETC Rp 3.322.492.617. ETS review of the 14th week is 39 days, and to complete the project is EAC greater than Rp 82.137.617 of contract costs. While completing the project, EAS is 137 days, requiring additional work time for 12 days. Based on the results of the analysis conducted by the service provider must take appropriate fast action to avoid excessive over budget

References

I. Purwanto and D. Pujotomo, “Analisis Performansi Pekerjaan Proyek Pembangunan Mechanical – Electrical – Pumbling Gedung Sentraland Semarang Menggunakan Metode Earned Value Analysis,†Ind. Eng. Online J., vol. 5, p. 3.

J. Colin and M. Vanhoucke, “Setting tolerance limits for statistical project control using earned value management,†Omega (United Kingdom), vol. 49, pp. 107–122, 2014, doi: 10.1016/j.omega.2014.06.001.

S. Stanek and D. Kuchta, “Increasing earned value analysis efficiency for IT projects,†J. Decis. Syst., pp. 1–9, 2020, doi: 10.1080/12460125.2020.1783882.

A. Abdi, S. Taghipour, and H. Khamooshi, “A model to control environmental performance of project execution process based on greenhouse gas emissions using earned value management,†Int. J. Proj. Manag., vol. 36, no. 3, pp. 397–413, 2018, doi: 10.1016/j.ijproman.2017.12.003.

T. Khesal, A. Saghaei, M. Khalilzadeh, M. Rahiminezhad Galankashi, and R. Soltani, “Integrated cost, quality, risk and schedule control through earned value management (EVM),†J. Eng. Des. Technol., vol. 17, no. 1, pp. 183–203, 2019, doi: 10.1108/JEDT-07-2018-0119.

M. Sutrisna, E. Pellicer, C. Torres-Machi, and M. Picornell, “Exploring earned value management in the Spanish construction industry as a pathway to competitive advantage,†Int. J. Constr. Manag., vol. 20, no. 1, pp. 1–12, 2020, doi: 10.1080/15623599.2018.1459155.

K. Agatha and D. H. Dani, “Pengendalian Biaya dan Jadwal Proyek dengan Menggunakan Nilai Hasil ( Proyek Rehabilitasi Gedung X Gresik ),†2018.

D. Kartika, “PENGENDALIAN BIAYA DAN WAKTU DENGAN METODE EARNED VALUE (Studi Kasus : Proyek Struktur dan Arsitektur Production Hall-02 Pandaan),†Tek. Sipil Untag Surabaya, vol. 7, no. 2, pp. 107–114, 2014.

D. Bryde, C. Unterhitzenberger, and R. Joby, “Conditions of success for earned value analysis in projects,†Int. J. Proj. Manag., vol. 36, no. 3, pp. 474–484, 2018, doi: 10.1016/j.ijproman.2017.12.002.

F. Ramdhani, “Analisis Biaya Dan Waktu Dengan Metode Earned Value Concept Pada Proyek BJDM Area RL Construction At Well 3S-21B Area 9 PT. Adhi Karya CS Work Unit Rate Packagea–Duri,†RACIC J. Tek. Sipil Univ. Abdurrab, vol. 1, no. 01, pp. 17–35, 2016.

Sambowo, F. N. Kharina, and K. Adi, “Analisis Keterlambatan Proyek Serta Dampaknya Terhadap Biaya Dan Waktu Pelaksanaan Proyek,†infrastruktur, vol. 5, pp. 13–19, 2019.

Romadhonnia, N. Aulady, M. F. Noor, and F. T. Nuciferani, “Pengukuran Kinerja Waktu Dan Biaya Proyek Pembangunan Jetty Menggunakan Metode Earned Value,†waktu, vol. 16, pp. 11–18, 2018.

Mahapatni Ida, A. P. Sri, Wirahaji, Bagus, Ida Wijaya, and Harta I Made, “Pengendalian Proyek dengan Earned Value Method (Evm) pada Proyek Pemeliharaan Jalan Provinsi Denpasar- Simpang Pesanggaran,†Widya Tek., vol. 13, no. 02, pp. 37–46, 2019, doi: 10.32795/widyateknik.v13i02.508.

I. Purwanto and D. Pujotomo, “Analisis Performansi Pekerjaan Proyek Pembangunan Mechanical – Electrical – Pumbling Gedung Sentraland Semarang Menggunakan Metode Earned Value Analysis,†Ind. Eng. Online J., vol. 5, p. 3.

J. Colin and M. Vanhoucke, “Setting tolerance limits for statistical project control using earned value management,†Omega (United Kingdom), vol. 49, pp. 107–122, 2014, doi: 10.1016/j.omega.2014.06.001.

S. Stanek and D. Kuchta, “Increasing earned value analysis efficiency for IT projects,†J. Decis. Syst., pp. 1–9, 2020, doi: 10.1080/12460125.2020.1783882.

A. Abdi, S. Taghipour, and H. Khamooshi, “A model to control environmental performance of project execution process based on greenhouse gas emissions using earned value management,†Int. J. Proj. Manag., vol. 36, no. 3, pp. 397–413, 2018, doi: 10.1016/j.ijproman.2017.12.003.

T. Khesal, A. Saghaei, M. Khalilzadeh, M. Rahiminezhad Galankashi, and R. Soltani, “Integrated cost, quality, risk and schedule control through earned value management (EVM),†J. Eng. Des. Technol., vol. 17, no. 1, pp. 183–203, 2019, doi: 10.1108/JEDT-07-2018-0119.

M. Sutrisna, E. Pellicer, C. Torres-Machi, and M. Picornell, “Exploring earned value management in the Spanish construction industry as a pathway to competitive advantage,†Int. J. Constr. Manag., vol. 20, no. 1, pp. 1–12, 2020, doi: 10.1080/15623599.2018.1459155.

K. Agatha and D. H. Dani, “Pengendalian Biaya dan Jadwal Proyek dengan Menggunakan Nilai Hasil ( Proyek Rehabilitasi Gedung X Gresik ),†2018.

D. Kartika, “PENGENDALIAN BIAYA DAN WAKTU DENGAN METODE EARNED VALUE (Studi Kasus : Proyek Struktur dan Arsitektur Production Hall-02 Pandaan),†Tek. Sipil Untag Surabaya, vol. 7, no. 2, pp. 107–114, 2014.

D. Bryde, C. Unterhitzenberger, and R. Joby, “Conditions of success for earned value analysis in projects,†Int. J. Proj. Manag., vol. 36, no. 3, pp. 474–484, 2018, doi: 10.1016/j.ijproman.2017.12.002.

F. Ramdhani, “Analisis Biaya Dan Waktu Dengan Metode Earned Value Concept Pada Proyek BJDM Area RL Construction At Well 3S-21B Area 9 PT. Adhi Karya CS Work Unit Rate Packagea–Duri,†RACIC J. Tek. Sipil Univ. Abdurrab, vol. 1, no. 01, pp. 17–35, 2016.

Sambowo, F. N. Kharina, and K. Adi, “Analisis Keterlambatan Proyek Serta Dampaknya Terhadap Biaya Dan Waktu Pelaksanaan Proyek,†infrastruktur, vol. 5, pp. 13–19, 2019.

Romadhonnia, N. Aulady, M. F. Noor, and F. T. Nuciferani, “Pengukuran Kinerja Waktu Dan Biaya Proyek Pembangunan Jetty Menggunakan Metode Earned Value,†waktu, vol. 16, pp. 11–18, 2018.

Mahapatni Ida, A. P. Sri, Wirahaji, Bagus, Ida Wijaya, and Harta I Made, “Pengendalian Proyek dengan Earned Value Method (Evm) pada Proyek Pemeliharaan Jalan Provinsi Denpasar- Simpang Pesanggaran,†Widya Tek., vol. 13, no. 02, pp. 37–46, 2019, doi: 10.32795/widyateknik.v13i02.508.

Alfian, “Evaluasi Pengendalian Biaya Dan Waktu Pada Proyek Pembangunan Jalan Strategis Matang Sijuek-Trieng Pantang Dengan Menggunakan,†Tek. Sipil Portal, vol. 8, no. 2, pp. 14–20, 2016.

A. Bakhtiar, “Proyek Peningkatan Jalan Menggunakan Metode Earned Value,†Teras J., vol. 8, no. 2, pp. 401–408, 2018, doi: http://dx.doi.org/10.29103/tj.v8i2.172.

E. Sari Ayu, “PENERAPAN EARNED VALUE ANALYSIS (Studi Kasus: Proyek Pembangunan Intake dan Jaringan Pipa Transmisi Air Baku Batang Mahat Kabupaten Lima Puluh Kota),†J. REKAYASA, vol. 07, no. 02, pp. 75–87, 2017.

B. Susanti, M. Melisah, and I. Juliantina, “Penerapan Konsep Earned Value Pada Proyek Konstruksi Jalan Tol (Studi Kasus Ruas Jalan Tol Kayuagung - Palembang -Betung),†J. Rekayasa Sipil, vol. 15, no. 1, p. 12, 2019, doi: 10.25077/jrs.15.1.12-20.2019.

S. Prasetya, N. W. Setyanto, C. Farela, and M. Tantrika, “PENERAPAN KONSEP EARNED VALUE METHOD SEBAGAI ALAT UKUR KINERJA BIAYA DAN JADWAL PADA PEKERJAAN BEKISTING ( Studi kasus : Proyek Pembangunan The Rimba Ayana Hotel oleh PT Anda Jaya Perkasa ) APPLICATION of EARNED VALUE METHOD CONCEPT for COST and SCHEDULE,†J. Rekayasa dan Manaj. Sist. Ind., no. 2008, pp. 24–35, 2011.

L. L. Willems and M. Vanhoucke, “Classification of articles and journals on project control and earned value management,†Int. J. Proj. Manag., vol. 33, no. 7, pp. 1610–1634, 2015, doi: 10.1016/j.ijproman.2015.06.003.

A. Susanty, A. L. Pekerti, and D. P. Sari, “Analisis Kinerja Proyek Pembangunan Rumah Sakit Banyumanik Ii Dengan Menggunakan Earned Value Analysis (Eva) Dan Project Evaluation Review Technique (Pert),†undip J. Tek. Ind., vol. 11, no. 2, p. 61, 2016, doi: 10.14710/jati.11.2.61-72.

A. Ridwan and R. Ajiono, “Pengendalian Biaya Dan Jadual Terpadu Pada Proyek Konstruksi,†UKaRst, vol. 1, no. 1, pp. 74–83, 2017.

A. Mishakova, A. Vakhrushkina, V. Murgul, and T. Sazonova, “Project Control Based on a Mutual Application of Pert and Earned Value Management Methods,†Procedia Eng., vol. 165, pp. 1812–1817, 2016, doi: 10.1016/j.proeng.2016.11.927.

PlumX Metrics

Published

2020-10-31

How to Cite

Damara, B. (2020). COST PERFORMANCE ANALYSIS AND TIME DEVELOPMENT CONSTRUCTION PROJECT BRIDGE CHAIN KARANGGENENG NAWACITA CS USING THE EARNED VALUE METHOD. UKaRsT, 4(2), 177–191. https://doi.org/10.30737/ukarst.v4i2.1067

Issue

Section

Articles