Construction work accidents become part of construction activities that need to be considered. Work accidents cause considerable losses so that there needs to be proper management of the work safety system. Definition of the risks that occur in construction activities can be done to reduce losses incurred. This research aims to categorize the risk of work accidents that occur in the Trenggalek Regency Pon Market development project. Categorize is done using the risk assessment matrix according to AS /NZS 4360:2004 so that the risk grouping category is obtained. Research methods use quantitative descriptive. The research population of 100 workers consisting of team leaders, architectural experts, structural civil experts, mechanical experts, experts, drafters, project administration, supervisors, artisans and workers with a total of 50 respondents. Data collection is done by distributing questionnaires to respondents. From the results of the questionnaire conducted validity testing and reliability test using IBMSPSS Statistic software. The results of the study obtained the risks that occurred categorized at low and medium levels. At the medium level probability with a scale often occurs that is the type of wound on the limbs. While probability with scale can occur at any time, namely the type of injury on the hand. So that from these results, risk control can be done and what things must be done to avoid work accidents in the Trenggalek Regency Pon Market development project.

References

H. Prasetiawan, A. Ridwan, and Y. Cahyo, “Evaluasi Pengendalian Mutu Pada Proyek Pembangunan Obyek Wisata Sedudo Di Kabupaten Nganjuk,†J. Manaj. Teknol. Tek. Sipil, vol. 2, no. 1, p. 65, 2019, doi: 10.30737/jurmateks.v2i1.392.

M. Kraus, “Risk assessments of contemporary accidents in construction industry,†MATEC Web Conf., vol. 146, pp. 1–6, 2018, doi: 10.1051/matecconf/201814603004.

W. Hartono, H. N. Rahmah, and Sugiyarto, “Identifikasi Bahaya dan Penilaian Risiko dalam Pekerjaan Pengecoran Beton untuk Proyek Gedung dengan Metode Analytic Hierarchy Process ( AHP ),†Matriks Tek. Sipil, no. 2004, pp. 25–32, 2016.

F. Tamim and A. Ismail, “Analisis Manajemen Risiko dan Pengendalian Kesehatan dan Keselamatan Kerja (K3) pada Pekerjaan Power House,†J. Konstr., vol. 18, no. 1, pp. 1–10, 2020, doi: 10.33364/konstruksi/v.18-1.772.

N. Xia, Q. Xie, M. A. Griffin, G. Ye, and J. Yuan, “Antecedents of safety behavior in construction: A literature review and an integrated conceptual framework,†Accid. Anal. Prev., vol. 148, no. March, p. 105834, 2020, doi: 10.1016/j.aap.2020.105834.

N. F. Fatmawaty Mallapiang, Dwi Santy Damayati, “Gambaran Perilaku Tenaga Kerja Dan Pelaksa- Naan Program Kesehatan Dan Keselamatan Kerja (K3) Konstruksi Dalam Pembangunan Balai Diklat Bpk - Ri Makassar Oleh PT. Wijaya Karya (Persero) Tbk,†Al-Sihah Public Heal. Sci. Journa, vol. 9, no. 1, pp. 72–84, 2017.

Y. Saraswati, A. Ridwan, and A. Iwan Candra, “Analisis Penerapan Keselamatan Dan Kesehatan Kerja (K3) Pembangunan Gedung Kuliah Bersama Kampus C Unair Surabaya,†J. Manaj. Teknol. Tek. Sipil, vol. 3, no. 2, pp. 247–260, 2020, doi: 10.30737/jurmateks.v3i2.1111.

X. Zhang and S. R. Mohandes, “Occupational Health and Safety in green building construction projects : A holistic Z-numbers-based risk management framework,†J. Clean. Prod., vol. 275, p. 122788, 2020, doi: 10.1016/j.jclepro.2020.122788.

R. Tanumihardja and M. R. A. Simanjuntak, “Risk identification in procurement of glass facade in high-rise office buildings in Jakarta,†IOP Conf. Ser. Mater. Sci. Eng., vol. 1007, no. 1, 2020, doi: 10.1088/1757-899X/1007/1/012092.

D. S. A. Yafi, “Assessment Risiko Kesehatan dan Keselamatan Kerja (K3) Menurut Variabel OHSAS dengan Menggunakan Metode HIRA, HAZID dan HAZOP,†Fak. Tek. Univ. Jember, pp. 28–37, 2018.

U. Yuliani, “Manajemen Risiko Keselamatan dan Kesehatan Kerja (K3) Pada Infrastruktur Gedung Bertingkat,†J. Desain Konstr., vol. 16, no. 1, pp. 92–100, 2017.

A. I. C. S. Susanto, Hendy , Sumargono, B. Winarno, “Measurement Of Occupational Safety And Health Risk Levels Of Kadiri University LP3M Building,†U KaRsT, vol. 5, no. 1, pp. 126–141, 2020, doi: 10.1016/j.proeng.2016.11.753.A.

I. W. H. Fung, V. W. Y. Tam, T. Y. Lo, and L. L. H. Lu, “Developing a risk assessment model for construction safety,†Int. J. Proj. Manag., vol. 28, no. 6, pp. 593–600, 2010, doi: 10.1016/j.ijproman.2009.09.006.

A. M. Keshk, I. Maarouf, and Y. Annany, “Special studies in management of construction project risks , risk concept , plan building , risk quantitative and qualitative analysis , risk response strategies,†Alexandria Eng. J., vol. 57, no. 4, pp. 3179–3187, 2018, doi: 10.1016/j.aej.2017.12.003.

AS/NZS 4360, “AS/NZS 4360. Australian/New Zealand Risk Manaement,†Aust. Stand. / New Zel. Stand. 43602004, p. 30, 2004.

E. Triswandana, “Penilaian Risiko K3 dengan Metode HIRARC,†UKaRsT, vol. 4, no. 1, p. 96, 2020, doi: 10.30737/ukarst.v4i1.788.

S. Al-Anbari, A. Khalina, A. Alnuaimi, A. Normariah, and A. Yahya, “Risk assessment of safety and health (RASH) for building construction,†Process Saf. Environ. Prot., vol. 94, no. C, pp. 149–158, 2015, doi: 10.1016/j.psep.2015.01.009.

A. Susanti, R. A. A. Soemitro, H. Suprayitno, and V. Ratnasari, “Searching the Appropriate Minimum Sample Size Calculation Method for Commuter Train Passenger Travel Behavior Survey,†J. Infrastruct. Facil. Asset Manag., vol. 1, no. 1, pp. 47–60, 2019, doi: 10.12962/jifam.v1i1.5232.

Sugiyono, Metode penelitian pendidikan pendekatan kuantitatif, kualitatif dan R&D. 2013.

D. O. Putri, B. Triatmanto, and S. Setiyadi, “The effect of occupational health and safety, work environment and discipline on employee performance in a consumer goods company,†IOP Conf. Ser. Mater. Sci. Eng., vol. 337, no. 1, 2018, doi: 10.1088/1757-899X/337/1/012036.

Purbayu Budi, “Analisis Statistik Dengan Microsoft Excel Dan Spss,†Andi, Yogyakarta, 2005.

Hardani et al., Metode Penelitian Kualitatif dan Kuantitatif, no. March. 2015.

H. T. Tjendani, R. Marleno, Hendry, and I. Subiyantoro, “Risk Assessment of Feasibility Study for Toll Road X - Y with Public Private Partnership (PPP) Scheme,†U KaRsT, vol. 4, no. 1, pp. 559–570, 2020.

B. Suhardi, A. A. V. Estianto, and P. W. Laksono, “Analysis of potential work accidents using hazard identification, risk assessment and risk control (HIRARC) method,†2016 2nd Int. Conf. Ind. Mech. Electr. Chem. Eng. ICIMECE 2016, pp. 196–200, 2017, doi: 10.1109/ICIMECE.2016.7910457.

N. L. A. Othman, N. S. Hussain, D. Ibrahim, and Y. Yaacob, “Safety and risk evaluation implementation at sheet metal stamping company using HIRARC model,†IOP Conf. Ser. Mater. Sci. Eng., vol. 670, no. 1, pp. 0–5, 2019, doi: 10.1088/1757-899X/670/1/012070.

A. D. Prabaswari, D. A. Susanti, B. W. Utomo, and B. R. Shintira, “Work Hazard Risk Analysis and Control in Grey Finishing Department Using HIRARC (Hazard Identification, Risk Assessment and Risk Control),†IOP Conf. Ser. Mater. Sci. Eng., vol. 982, no. 1, 2020, doi: 10.1088/1757-899X/982/1/012053.

PlumX Metrics

Published

2021-10-31

Issue

Section

Articles