Efektivitas Dinding Sandwich Panel dan Precast ACC Panel Terhadap Biaya dan Waktu

Authors

  • Kholis Hapsari Program Studi Teknik Sipil, Fakultas Teknik, Universitas Sebelas Maret, Surakarta, Indonesia
  • Ardia Tiara Rahmi Program Studi Teknik Sipil, Fakultas Teknik, Universitas Sebelas Maret, Surakarta, Indonesia
  • Delista Putri Deni Program Studi Teknik Sipil, Fakultas Teknik, Universitas Sebelas Maret, Surakarta, Indonesia

DOI:

https://doi.org/10.30737/jurmateks.v6i2.5126

Keywords:

Budget, Duration, Precast AAC Panel, Sandwich Panel

Abstract

Project delays in construction development have a major impact, especially on costs. Projects that experience delays in implementation will require large costs. One of the delay factors is caused by material selection, especially for wall materials. Precast AAC Panel wall and sandwich panel walls are current wall material innovations, but both differ in material composition, implementation method, and price. This research aims to analyze the effectiveness of the two types of walls in terms of cost and time. The research will use objects from the 24-story Sudimaran Forestwalk apartment development in South Tangerang. The research method uses quantitative methods by making a cost budget plan obtained from data on work volume, productivity, and unit price of work. Next, analyze the duration of work from productivity data and work volume. The analysis results for the budget for work costs using precast AAC panel materials cost IDR 11,640,163,103, while sandwich panel walls are IDR 16,223,117,608. For comparison of implementation time, precast AAC panel walls are faster, with a work duration of 623 days, and sandwich panel walls 784 days. From these price results, AAC panel walls are 23% cheaper than sandwich panel walls. Due to the low strength, the sandwich panel walls are sometimes damaged during construction, resulting in longer construction times. The analysis results show that precast AAC panel walls are more recommended as the choice of wall type in terms of cost and implementation time.

References

W. P. O. Y. Devi1, “Keberadaan Apartemen dan Pengaruhnya Terhadap Aktivitas Sosial dan Ekonomi Kawasan Seturan, Yogyakarta,” PWK UNDIP, vol. 6, no. 2, pp. 86–97, 2017.

M. C. Winoto, K. Guwinarto, and S. Limanto, “Faktor Penyebab Dan Dampak Keterlambatan Pelaksanaan Proyek Konstruksi Menurut Kontraktor Terhadap Indikator Performa Proyek,” Dimens. Pratama Tek. Sipil, vol. 12, pp. 57–63, 2023.

A. D. Intan Purnama Ajar, “Analisis Perbandingan dan Waktu Pada Pekerjaan Dinding Deywall (Praktisi Rockwall) dan Batako Press Studi Kasus Proyek Pembangunan Ayana North Wing – Bali,” vol. 1, no. 1, pp. 96–103, 2021.

B. R. K. Holla, S. Anant, M. A. Mohammad, A. Periwal, and A. Kapoor, “Time, Cost , Productivity and Quality Analysis of Precast Concrete System,” Int. J. Innov. Sci. Eng. Technol., vol. 3, no. 5, pp. 252–257, 2016.

S. Y. Putri and A. Setiawan, “Perbandingan Dinding Prefab Cement Wall Dengan Bata Konvensional Pada Bangunan Rumah,” no. November, pp. 1–2, 2017.

W. Prana, Made; Muka, “Perbandingan Waktu Dan Biaya Pada Pekerjaan Pasangan Dinding Dengan Metode Time Study Pada Proyek Konsruksi Gedung,” vol. 013, no. 01, 2020.

E. B. Ma’ruf Syafaat, Mardewi Jamal, “Analisis Perhitungan Waktu dan Biaya Antara Bandara Pattimura Ambon,” J. Unmul, vol. 5, no. November, pp. 42–49, 2021, doi: DOI: http://dx.doi.org/10.30872/ts.v5i2.6985.

Yusuf, “Aplikasi Panel lantai AAC Dengan Material Pendukungnya,” p. 282, Dec. 2021.

L. T. Herianto and G. Y. Malingkas, “Metode Pelaksanaan Pekerjaan Dinding Pasangan Bata Ringan Dan Plesteran Pada Pekerjaan Proyek Office and Distribution Centre Pt.Sukanda Jaya Airmadidi-Minahasa Utara,” J. Sipil Statik, vol. 8, no. 5, pp. 695–708, 2020.

I. P. Suharto and H. Sulistio, “Produktivitas Pekerja Dalam Pekerjaan Plesteran Dinding Bata Dengan Metode Crew Balance Chart,” JMTS J. Mitra Tek. Sipil, vol. 3, no. 4, p. 1373, 2020, doi: 10.24912/jmts.v3i4.8378.

V. Febriyanto, Perbandingan Analisis Harga Satuan Pekerjaan (AHSP) terhadap Harga Borongan Upah di Lapangan. 2022.

B. A. Husain, J. B. Mangare, and P. A. K. Pratasis, “Produktivitas Pasangan Dan Plesteran Dinding Bata Ringan Pada Kasus Pembangunan Mess Dan Prasarana DENMADAM XIII/MDK,” Tekno, vol. 20, no. 81, pp. 203–207, 2022.

I. Akbar, M. Wijayaningtyas, and L. A. Ratnawinanda, “Analisis Koefisien Produktivitas Pasangan Dinding Bata Ringan Gedung Keolahragaan Universitas Negeri Malang,” Gelagar Student J., vol. 2, no. 1, pp. 1–8, 2020.

R. Rizal, P. T. Juwono, and R. Haribowo, “Studi Manajemen Konstruksi Proyek Rehabilitasi Bendungan Simo di Kabupaten Grobogan dengan Menggunakan Program Microsoft Project Manager 2016,” J. Teknol. dan Rekayasa Sumber Daya Air, vol. 2, no. 1, pp. 1–40, 2022, doi: 10.21776/ub.jtresda.2022.002.01.03.

S. El Unas, K. Puspa N., and R. R. P. Yudha, “Analisa Produktivitas Pekerjaan Dinding Panel, Dinding Batu Bata Konvensional, Dan Sni Pekerjaan Dinding,” J. Mhs. Jur. Tek. Sipil, vol. 1, no. 2, p. pp-243, 2015.

A. P. Biaya, F. Hidayat, and G. Irvan, “Tata Laksana Pekerjaan Dinding Menggunakan Bata Ringan , Sandwich Panel dan Beton Precast pada Proyek Pembangunan Rumah Sakit ‘ STC ’ di Kota Jakarta,” vol. 7, no. November, pp. 40–51, 2018.

Moh. Yusuf Hasbi, “Desain Permodelan Dinding Beton Ringan Precast Rumah Tahan Gempa Berbasisi Knocdown System,” Institut Tekhnologi Sepuluh Novmber, 2021.

A. Wisselly and W. Kushartomo, “Analisis Sambungan Purus (Tongue and Groove Joints) Pada Dinding Panel Beton Ringan Styrofoam,” JMTS J. Mitra Tek. Sipil, vol. 6, no. 2, pp. 217–222, 2023, doi: 10.24912/jmts.v6i2.21667.

B. Industries, “Katalog-LeichtPanel,” Broco Industries, pp. 1–13, 2020. [Online]. Available: http://brocoindustries.com/pdf/leicht-panel-2020.pdf

K. Wang and K. Ding, “applied sciences Experimental Study on the Seismic Performance of New Energy Dissipation Connectors in an Autoclaved Aerated Concrete Panel with Assembled Steel Frame,” 2022.

E. Utomo, A. Zubaydi, and P. Pratisna, “Study of Core Material Sandwich Panel In Ship Construction,” 2nd Int. Semin. Sci. Technol., 2017.

G. A. Y. P. A. Khadafi Anugerahanto, “Perbandingan Pekerjaan Dinding Precast dan Dinding Konvensional pada Konstruksi High Rise Building Ditinjau Dari Segi Waktu dan Biaya,” Rekayasa Tek. Sipil UNESA, pp. 1–9, 2018.

N. Safaah and S. Wacono, “Analisis perbandingan harga satuan pekerjaan kolom pada proyek southside apartment,” Semin. Nas. Tek. Sipil Politek. Negeri Jakarta, pp. 290–299, 2019.

A. D. Esa Putera Wibawa, “Analisis Efektivitas Penggunaan Sandwich Panel dan Bata Ringan Terhadap Proyek Penanganan COVID-19 Studi Kasus RS . Cipto Mangunkusumo - Jakarta,” J. Artesis, vol. 2, no. 1, pp. 32–39, 2022.

K. Y. Pratama, S. S. Riskijah, and F. Purnomo, “Rencana pelaksanaan dinding luar precast pada proyek pembangunan apartemen x,” vol. 3, pp. 36–41, 2022.

L. Khamelda, B. S. Yoedono, and A. Catharina S.P.S, “Analisis Perbandingan Karakteristik, Biaya dan Waktu Material Dinding Komposit dan Non Komposit,” Reka Buana J. Ilm. Tek. Sipil dan Tek. Kim., vol. 3, no. 2, p. 108, 2018, doi: 10.33366/rekabuana.v3i2.1017.

C. Hardianta and M. Effendy, “Penjadwalan Proyek Dengan Kurva S Berbasis Tenaga Kerja Pada Proyek Pembangunan Perumahan,” Semin. Keinsinyuran Progr. Stud. Progr. Profesi Ins., vol. 1, no. 2, pp. 565–572, 2021, doi: 10.22219/skpsppi.v2i1.4434.