Mempercepat Waktu Pelaksanaan Proyek Pembangunan Jalur Ganda Kereta Api Antara Mojokerto-Sepanjang Melalui Penjadwalan Line of Balance
DOI:
https://doi.org/10.30737/jurmateks.v5i2.4020Keywords:
Line Of Balance, Overlapping Jobs, Project Scheduling, Recurring JobsAbstract
In construction management, project scheduling is an important thing to note. The project schedule is a means of determining proper duration, controlling implementation progress, and allocating resources efficiently. Improper scheduling will have an impact on project delays. the project for the construction of a double track railway across the south of Java between Mojokerto-Sepanjang is planned to be completed in 60 weeks with overlapping activities due to changes in activities. This double track rail project is an ongoing project. This research aims to find out the project implementation time using the Line of Balance. The development project has a length of 3011.23 m. the Line of Balance method is carried out by determining the dependency logic, preparing a Line Of Balance schedule, drawing a Line Of Balance graph, and determining the production speed. The results of the study show that the line of balance schedule in the existing conditions has lines of intersection between jobs. The intersection indicates that there is overlapping work. For this reason, improvements are made by changing the dependency logic from work that was originally parallel to not parallel. The results of improvements made by reducing the duration per work cycle by 1 week revealed that the duration of the project could be accelerated to 38 weeks. So that the scheduling can be used to speed up the time of implementation of project activities.References
E. Kamitono, V. William, and P. Chandra, “Perencanaan Jadwal Pada Proyek Perumahan Dengan Metode Line of Balance,†J. Dimens. Pratama Tek. Sipil, vol. 9, no. 2, pp. 86–93, 2018, [Online]. Available: https://publication.petra.ac.id/index.php/teknik-sipil/article/view/10665
Y. Simamora and W. Nuswantoro, “Studi Penjadwalan Waktu dengan Metode Line Of Balance ( LOB ) untuk Membangun Perumahan Pasca Bencana Tsunami Di NAD (Studi Kasus Pembangunan Perumahan Di Calang),†J. Manaj. Rekayasa Konstr., vol. 9, no. 1, pp. 1–9, 2018, [Online]. Available: https://www.researchgate.net/publication/324686690
M. J. Fuad, “Penjadwalan dan Alokasi Material Dengan Metode Line Of Balance (LOB) Pada Proyek Pelebaran Jalan AP.Pettarani Utara Makassar,†vol. 7, no. 2, pp. 153–161, 2019, doi: https://doi.org/10.37971/radial.v7i2.193.
H. Meidiyanto, “Implementasi Line Of Balance dan M-PERT pada Pekerjaan Wastewater Treatment Plant,†Universitas Mercubuana, 2019. [Online]. Available: https://repository.mercubuana.ac.id/id/eprint/59236
K. F. Abidin, “Analisis Optimasi Penjadwalan Proyek dan Efisiensi Biaya Pada Proyek Pembangunan Gedung: (Studi Kasus Pembangunan RSUD Ketanggungan Kabupaten Brebes),†Universitas Islam Sultan Agung Semarang, 2021. [Online]. Available: https://www.proquest.com/openview/28b498cb3f0be8a36c59f09c0e4f044a/1.pdf?pq-origsite=gscholar&cbl=2026366&diss=y
Y. Juniardi, I. Lakawa, and hujiyanto, “The Influence of Discipline and Training on Teacher Performance in Junior High Schools,†IJMEHD Int. J. Manag. Educ. Hum. Dev., vol. 02, no. 01, pp. 79–84, 2021, [Online]. Available: https://ijmehd.com/index.php/ijmehd/article/download/54/52
A. Efendi, A. Dwiretnani, and A. Setiawan, “Analisa Penjadwalan Proyek dengan Menggunakan Metode Line Of Balance (LOB) pada Proyek Pedestrian Jl. MH. Thamrin-Jl. Halim Perdana Kusuma,†J. Talent. Sipil, vol. 5, no. 2, pp. 346–353, 2022, doi: 10.33087/talentasipil.v5i2.137.
Y. Dwi, “Analisis durasi penjadwalan ulang proyek pembangunan perumahan dengan menggunakan metode LSM ( linear scheduling method ),†Universitas Islam Riau, 2019. [Online]. Available: http://repository.uir.ac.id/id/eprint/9285
N. L. Maspaitella, “Tinjauan Waktu Pelaksanaan Proyek IKP residence Sorong Dengan Metode LoB,†Univ. Muhammadiyah Sorong, no. 27, pp. 1–4, 2019, [Online]. Available: https://osf.io/preprints/inarxiv/6jzw7/download
N. Soplanit, N. Maelissa, and H. D. Titaley, “Analisis Penerapan Metode Line Of Balance Pada Pembangunan Rumah Susun Pemkab Kepulauan Tanibar,†SIMETRIK, vol. 11, no. 2, pp. 474–479, 2021, doi: https://doi.org/10.31959/js.v11i2.773.
G. Nugrianto, M. Syambas, R. Diky, and N. Demus, “Analisis Penerapan Line Balancing untuk Peningkatan Efisiensi pada Proses Produksi Pembuatan Pagar Besi Studi Kasus : CV . Bumen Las Kontraktor,†Bull. Appl. Ind. Eng. Theory, vol. 1, no. 2, pp. 46–53, 2020, [Online]. Available: http://jim.unindra.ac.id/index.php/baiet/article/view/2842
I. Gunawan, “Digital Digital Repository Repository Universitas Universitas Jember Jember Digital Digital Repository Repository Universitas Universitas Jember Jember,†Universitas Jember, 2019. [Online]. Available: http://repository.unej.ac.id/handle/123456789/101304
J. Halimi, “Analisis Penjadwalan Ulang Dengan Menggunakan Metode LSM (Linier Scheduling Method/ Line Of Balance) (Rescheduling Analysis With LSM/LOB Method),†Universitas Islam Indonesia, 2018. [Online]. Available: https://dspace.uii.ac.id/handle/123456789/6778
R. Susanti and Lukman, “Studi Eksplorasi Metode Penjadwalan Pada Proyek Konstruksi Jalan Tol Semarang-Solo Ruas Ungaran-Bawen,†J. Proy. Tek. Sipil, vol. 2, no. 1, pp. 1–13, 2019, doi: https://doi.org/10.14710/potensi.2019.3607.
J. D. Hutagaol, S. M, M. A. Wibowo, and S. T. S, “Perbandingan Metode Critical Path Method (CPM), Predence Diagram Method (PDM), dan Line Of Balance (LOB) Terhadap Proyek Repetitif,†J. Karya Tek. Sipil, vol. 2, no. 1, pp. 205–227, 2013, [Online]. Available: https://ejournal3.undip.ac.id/index.php/jkts/article/view/4108
I. W. Y. Astawa, N. K. T. Tastrawati, and L. P. I. Harini, “Waktu Penyelesaian Proyek Konstruksi Menggunakan Precedence Diagram Method dan Line Of Balance,†E-Jurnal Mat., vol. 9, no. 3, pp. 190–196, 2020, doi: https://doi.org/10.24843/MTK.2020.v09.i03.p298.
L. N. Saskia, “Analisis Penggunaaan Metode Penjadwalan Line of Balance Pada Proyek Kosntruksi Repetitif,†JUTATEKS, vol. 4, no. 1, pp. 91–98, 2021, [Online]. Available: https://ojs.poltekba.ac.id/ojs/index.php/jutateks/article/view/261
F. Laia, “Penerapan Metode Line Of Balance Pada Penjadwalan Proyek Jalan Preservasi Teluk Dalam-Lolowau,†Universitas Medan Area, 2020. [Online]. Available: http://repository.uma.ac.id/handle/123456789/16137
E. A. Laksono, “Analisis Penjadwalan Ulang Waktu Pelaksanaan Proyek Pembangunan Jalur Ganda Kereta Api Kroya – Kutoarjo KM 438+600 Sampai dengan 446+800 Antara Gombong – Soka Dengan Metode Line Of Balance,†Universitas Islam Indonesia, 2019. [Online]. Available: http://hdl.handle.net/123456789/16016
O. Z. Dahlan, “Analisis Perbandingan Biaya Dan Waktu Antara Penjadwalan Dengan Barchart Dan Linear Scheduling Method ( Comparative Analysis of Costs and Time on Scheduling Using Barchart and Linear Method ),†Universitas Islam Indonesia, 2018. [Online]. Available: https://dspace.uii.ac.id/handle/123456789/11290
Y. Pratiwi, “Penggunaan Line Of Balance Pada Perkerasan Kaku Di Proyek Pembangunan Jalan TOL Tebing Tinggi – Inderapura,†Universitas Medan Area, 2022. [Online]. Available: http://110.232.83.118/jspui/bitstream/123456789/17512/2/168110087_Yuli Pratiwi_Fulltext.pdf
A. P. A. Putra and G. Sarya, “Analisis Penjadwalan dan Alokasi Biaya Menggunakan Metode Line Of Balance Pada Proyek Jalan dan Jembatan Frontage Road Waru-Buduran,†vol. 5, no. 1, pp. 390–397, 2022, doi: http://dx.doi.org/10.31602/jk.v5i1.7568.
A. Maddeppungeng, A. Budiman, and G. Christopher, “Metode Keseimbangan Garis ( Line Of Balance ) Pada Penjadwalan Proyek Repetitif,†J. Konstr., vol. 14, no. 1, pp. 88–106, 2022, [Online]. Available: https://doi.org/10.24853/jk.14.1.88-106
A. Silvia, D. Sarasanty, and E. Soewartono, “Analisa Perbandingan Waktu Dan Biaya Metode Konvensional Dengan Flat Slab Struktur Pelat Lantai Apartemen Grand Dharmahusada Lagoon Surabaya,†Universitas Islam Majapahit, 2020. [Online]. Available: http://repository.unim.ac.id/id/eprint/1035
W. Ramadhina, “Analisa Pengendalian Waktu Proyek dengan Menggunakan Metode LoB (Line of Balance) Pada Proyek Perumahan dan Ruko Citraland Driyorejo CBD,†Universitas 17 Agustus 1945 Surabaya, 2022. [Online]. Available: http://repository.untag-sby.ac.id/id/eprint/16670
Downloads
Published
Issue
Section
License
Authors who publish with this journal agree to the following terms:
(1) The copyright of published articles will be transferred to the journal as the publisher of the manuscript. Therefore, the author needs to confirm that the copyright has been managed by the publisher with the Publication Right Form which must be attached when submitting the article.
(2) Publisher of JURMATEKS is Kadiri University.
(3) The copyright follows Creative Commons Attribution-ShareAlike License (CC BY SA): This license allows to Share copy and redistribute the material in any medium or format, Adapt remix, transform, and build upon the material, for any purpose, even commercially.