Optimasi Waktu dan Biaya Proyek Gelanggang Olahraga Kalimantan Selatan dengan Metode Time Cost Trade-Off

Authors

  • Endah Widiastuti Universitas Lambung Mangkurat
  • Maesa Fitri Sugiarti Universitas Lambung Mangkurat
  • Candra Yuliana Universitas Lambung Mangkurat
  • Abdul Karim Universitas Lambung Mangkurat

DOI:

https://doi.org/10.30737/jurmateks.v8i1.6597

Keywords:

Cost Slope, Critical Path, Crashing, Overtime, Time Cost Trade Off (TCTO)

Abstract

Construction projects often face delays and cost overruns due to material delays, labor shortages, and adverse weather. In the Sports Building project in South Kalimantan, a 17-day delay beyond the planned 270-day schedule increased costs, risk of penalties, and threatened the contractor’s reputation and project sustainability. Therefore, accelerating completion is essential to reduce losses. Overtime on critical path activities is a common acceleration method but requires careful analysis since excessive overtime can reduce productivity and raise costs. This study aims to analyze alternatives for accelerating the duration of the construction of a sports arena in South Kalimantan using the Time Cost Trade-Off (TCTO) method. TCT) method is applied, focusing on adding 2, 3, and 4 hours of overtime per day on critical path tasks. The approach integrates actual project data, regulations, and productivity factors to develop effective acceleration strategies. Results show that adding 3 hours of overtime daily is the most efficient, reducing duration from 287 to 283 days and saving IDR 71,652,415.38. However, the 270-day target is not yet met, requiring further crashing. This paper presents only one crashing iteration as a practical simulation to demonstrate the method and potential outcomes. Future crashing will focus on tasks with the lowest cost slope while considering task dependencies.

References

[1] F. D. Akin, P. Gul, T. Harun, and A. and Damci, “A crashing-based time-cost trade-off model considering quality cost and contract clauses,” Int. J. Constr. Manag., vol. 23, no. 6, pp. 954–963, Jun. 2021, doi: 10.1080/15623599.2021.1946899.

[2] K. R. Srimathi, A. Padmarekha, and K. S. Anandh, “Automated construction schedule optimisation using genetic algorithm,” Asian J. Civ. Eng., vol. 24, no. 8, pp. 3521–3528, 2023, doi: 10.1007/s42107-023-00729-8.

[3] T. Rahmanto and S. Janizar, “Pengendalian Biaya Dan Waktu Dengan Metode Earned Value Proyek Familia Urban B.Ek.a.Si,” J. Tek. Sipil Cendekia, vol. 3, no. 2, pp. 16–27, 2022, doi: 10.51988/jtsc.v3i2.48.

[4] S. Sadri and S. M. T. and Fatemi Ghomi, “Evaluating time-cost trade-off in a resource constraint GERT-type project scheduling problem considering rework,” Int. J. Syst. Sci. Oper. Logist., vol. 11, no. 1, p. 2436194, Dec. 2024, doi: 10.1080/23302674.2024.2436194.

[5] J. Wang, Z. Wang, and H. Liu, “Multi-objective Stochastic Time-cost-quality Optimization for Construction Projects Based on the Reliability Theory,” KSCE J. Civ. Eng., vol. 27, no. 11, pp. 4545–4556, 2023, doi: 10.1007/s12205-023-1083-z.

[6] V. V Nazimko and L. M. and Zakharova, “Project Schedule Expediting under Structural and Parametric Uncertainty,” Eng. Manag. J., vol. 35, no. 1, pp. 29–49, Jan. 2023, doi: 10.1080/10429247.2022.2030179.

[7] R. Pratiwi, S. Mulia Devi, A. Marini, and H. Maya Sari, “Optimasi Waktu Dan Biaya Dengan Metode Time Cost Trade Off (Tcto) Pada Proyek Penambahan Bangunan Pasar Rakyat,” J. Ilm. Tek. Sipil TRANSUKMA, vol. 4, no. 2, pp. 93–105, 2022, doi: 10.36277/transukma.v4i2.134.

[8] H. Zou and G. and Zhou, “Multimode variable resource-constrained time/cost trade-off problem in repetitive projects with adjustment strategy,” Int. J. Constr. Manag., vol. 24, no. 12, pp. 1271–1281, Sep. 2024, doi: 10.1080/15623599.2023.2276650.

[9] T. I. K. Amar, F. F. Astuti, and ..., “Strategi Percepatan Proyek Dengan Metode Crashing Pada Pembangunan Drainase Di Pemukiman Padat Penduduk,” J. Tek. Sipil …, vol. 09, no. 02, pp. 74–81, 2023, [Online]. Available: http://ejournal.um-sorong.ac.id/index.php/rancangbangun/article/view/2632%0Ahttps://ejournal.um-sorong.ac.id/index.php/rancangbangun/article/download/2632/1482

[10] T. Wang, M. Abdallah, C. Clevenger, and S. Monghasemi, “Time–cost–quality trade-off analysis for planning construction projects,” Eng. Constr. Archit. Manag., vol. 28, no. 1, pp. 82–100, Jan. 2021, doi: 10.1108/ECAM-12-2017-0271.

[11] A. Alhady, A. A. Khaled, and S. and Mahfouz, “Time-cost quality risk trade-off for infrastructure projects in Egypt,” HBRC J., vol. 21, no. 1, pp. 234–246, Dec. 2025, doi: 10.1080/16874048.2025.2473774.

[12] M. F. M. Djau and T. Inkiriwang, “Percepatan Pelaksanaan Proyek Dengan Penambahan Tenaga Kerja Pada Pembangunan Ruko Di Jalan Bukit Moria, Tikala Baru,” J. Sipil Statik, vol. 9, no. 4, pp. 709–716, 2021, [Online]. Available: https://ejournal.unsrat.ac.id

[13] A. K. Agarwal, S. S. Chauhan, K. Sharma, and K. C. Sethi, “Development of time–cost trade-off optimization model for construction projects with MOPSO technique,” Asian J. Civ. Eng., vol. 25, no. 6, pp. 4529–4539, 2024, doi: 10.1007/s42107-024-01063-3.

[14] I. Kusmaryono, N. C. Fertilia, R. Dewi, and F. Mahardika, “ANALISIS PERCEPATAN WAKTU PELAKSANAAN PEKERJAAN PADA PROYEK PEMBANGUNAN JALAN TOL MENGGUNAKAN METODE TIME COST TRADE OFF (Studi Kasus: Proyek Jalan Tol Cinere-Jagorawi Seksi 3),” J. Tek. Sipil, vol. 1, no. 1, pp. 40–49, 2022.

[15] H. Turkoglu, P. Gul, and F. D. and Akin, “Crashing construction projects considering schedule flexibility: an illustrative example,” Int. J. Constr. Manag., vol. 23, no. 4, pp. 619–628, Mar. 2023, doi: 10.1080/15623599.2021.1901559.

[16] E. Eliatun and D. Tjitradi, “Analisis Percepatan Dengan Metode Crashing Pada Proyek Pembangunan Gedung X Di Banjarmasin,” J. Kacapuri J. Keilmuan Tek. Sipil, vol. 5, no. 1, p. 72, 2021, doi: 10.31602/jk.v5i1.7230.

[17] S. Usman, A. H. Muhammad, I. Adjam, M. Kom, and I. Altarans, “Optimasi Biaya Dan Waktu Pelaksanaan Proyek Konstruksi Dengan Penambahan Jam Kerja Dan Penambahan Tenaga Kerja Menggunakan Metode Time Cost Trade Off (Studi Kasus: Proyek Pembangunan Gedung Islamic Center Halmahera Tengah),” Teknik, vol. 16, no. 1, pp. 2589–8891, 2023, [Online]. Available: www.jurnal.ummu.ac.id/dintek

[18] Y. Azzahra, L. Lusiana, R. Rafie, S. Syahrudin, and S. M. Nuh, “Time Cost Trade Off Analysis on Project Acceleration With Additional Working Hours (Overtime) (Case Study: Building Rehabilitation Project on Dekranasda Hall of West Kalimantan),” J. Tek. Sipil, vol. 23, no. 4, p. 564, 2024, doi: 10.26418/jts.v23i4.71535.

[19] E. A. Budianto and A. E. Husin, “Analisis Optimasi Waktu Dan Biaya Dengan Metode Time Cost Trade Off Pada Proyek Gudang Amunisi.,” J. Apl. Tek. Sipil, vol. 19, no. 3, p. 305, 2021, doi: 10.12962/j2579-891x.v19i3.9146.

[20] F. K. Wibowo et al., “Optimasi waktu dan biaya dengan metode crashing pada proyek pembangunan rumah susun,” Dsp. UII, pp. 1–12, 2020.

[21] S. Aulia, S. Setiono, and M. Rifai, “Cost and Duration Optimization at Building C of Dharmais Cancer Hospital Jakarta with TCTO Method Using Primavera P6 Analysis,” Sustain. Civ. Build. Manag. Eng., vol. 1, no. 4, p. 13, 2024, doi: 10.47134/scbmej.v1i4.2722.

[22] M. F. Faqihhuddin, A. Jl, I. Sutami, K. Jebres, K. Surakarta, and J. Tengah, “Analisis Biaya dan Waktu dengan Metode Time Cost Trade Off menggunakan Aplikasi Primavera P6 Flyover Pengganti JPL 64 Km 38 + 897 Lintas Surabaya-Solo melalui Balai Teknik Perkeretaapian Wilayah Jawa Bagian Timur dengan menghabiskan dana sebesar Rp Salah satu metode untuk mengatasi permasalahan dalam mencapai target biaya dan waktu proyek konstruksi adalah metode Time Cost Trade Off ( TCTO ). Metode TCTO adalah pendekatan yang digunakan dalam manajemen proyek konstruksi untuk mencapai proyek yang baik . Salah satu alat yang digunakan dalam manajemen konstruksi adalah aplikasi,” vol. 3, no. 3, 2025.

[23] C. Angelia, P. I. Mulyanto, and D. Chrismianto, “Aplikasi Metode Time Cost Trade Off Akibat Keterlambatan Bagian Mesin Pada Proyek Pembangunan Mooring Boat Milik PT. Pertamina Trans Kontinental,” Tek. Perkapalan, vol. 9, no. 3, pp. 283–2, 2021.

[24] F. Nabila, “A Analysis of Time and Cost Optimization in Building Contruction Using Time Cost Trade Off Method,” J. Civ. Eng. Plan., vol. 4, no. 2, pp. 199–210, 2023, doi: 10.37253/jcep.v4i2.8662.

[25] Peraturan Pemerintah RI, “Peraturan Pemerintah RI Nomor 5 Tahun 2021 tentang Penyelenggaraan Perizinan Berusaha Berbasis Resiko,” Peratur. Pemerintah, no. 087293, p. 390, 2021.

[26] A. Jalil and M. Taufiq, “Perppu,” Al-Ihkam J. Huk. dan Pranata Sos., vol. 14, no. 1, pp. 146–177, 2019, doi: 10.19105/al-lhkam.v14i1.1982.

[27] P. Perkiraan, B. Pekerjaan, K. Bidang, and P. Rakyat, “Peraturan Menteri PUPR Nomor 8 Tahun 2023,” no. 683, 2023, [Online]. Available: www.peraturan.go.id

[28] I. Soeharto, “Manajemen proyek dari konseptual sampai operasional,” 1997.

[29] V. M. Sorongan, A. K. T. Dundu, and J. Tjakra, “Analisa Penjadwalan Proyek Menggunakan Metode PDM dengan Menggunakan Konsep Cadangan Waktu pada Proyek Peningkatan Ruas Jalan Tondano-Kembes-Manado Seksi 2,” Tekno, vol. 20, no. 81, pp. 399–408, 2022.

[30] B. F. Tombokan, G. Y. Malingkas, and P. A. K Pratasis, “Analisis Hubungan Pekerjaan Dan Lintasan Kritis Pada Penjadwalan Proyek Pembangunan Rumah Sakit Umum Daerah Dr. Sam Ratulangi Tondano Menggunakan Metode Precedence Diagram Method,” J. Unsrat Tekno, vol. 20, no. 82, pp. 1041–1050, 2022, [Online]. Available: https://ejournal.unsrat.ac.id/

[31] H. Kerzner, Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons, 2025.

Downloads

Published

2025-09-30

Issue

Section

Articles

How to Cite

Optimasi Waktu dan Biaya Proyek Gelanggang Olahraga Kalimantan Selatan dengan Metode Time Cost Trade-Off. (2025). Jurnal Manajemen Teknologi & Teknik Sipil, 8(1), 79-92. https://doi.org/10.30737/jurmateks.v8i1.6597

Similar Articles

11-20 of 57

You may also start an advanced similarity search for this article.