ANALISA ANGGARAN BIAYA DANPENJADWALANPROYEK PERBAIKAN TANGGUL KALI BAKUNGDESA CENGKOK KECAMATAN TAROKAN KABUPATEN KEDIRI

Authors

  • Johan Harmawanto Fakultas Teknik Universitas Kadiri
  • Yosef Cahyo Setianto Poernomo Fakultas Teknik Universitas Kadiri
  • Sigit Winarto Fakultas Teknik Universitas Kadiri

DOI:

https://doi.org/10.30737/jurmateks.v2i2.514

Keywords:

Improvement, Cost, Schedule, Precedence Diagram Method (PDM)

Abstract

Bakung River is a medium to supply water demand for irrigation in Cengkok Village TarokanSubdistrict Kediri Regency. Unfortunately, the soil embankment often slides to disturb the irrigation. The writer made the cost estimate, scheduling, network, and undertaking method of improving the Bakung River embankment with river stone. The data obtained from the Department of Water Public Work (DWPW) were of technical drawings, specifications, the unit price of material, and construction work of Kediri Regency 2019. The result was analyzed to find out the unit price analysis of construction work; hence the cost analysis was made. The schedule was derived from making the cost estimate by calculating the work quantity and calculating the duration. The results were processed through MS Excel to make a bar chart, S Curve, and Precedence Diagram Method (PDM) as the network. The calculations result in IDR 914.486.100,00 and 91 workdays.

Kali Bakung merupakan sarana  untuk memenuhi kebutuhan air irigasi di Desa Cengkok Kecamatan Tarokan Kabupaten Kediri. Akan tetapi keadaan tanggul Kali Bakung mengalami kerusakan dan penyediaan air irigasi menjadi terganggu. Penulis membuat analisa anggaran biaya, penjadwalan, jaringan dan metode pelaksanaan untuk perbaikan tanggul Kali Bakung dengan pasangan batu kali. Data yang diperoleh dari Dinas Pekerjaan Umum Sumber Daya Air adalah gambar teknis, spesifikasi, harga satuan upah dan bahan Kabupaten Kediri tahun 2019. Hasilnya dianalisis untuk mengetahui analisa harga satuan pekerjaan, maka dibuat rencana anggaran biaya. Jadwal berasal dari rencana anggaran biaya dengan menghitung bobot pekerjaan dan menghitung durasi. Hasilnya diproses dengan MS Excel untuk membuat bar chart, kurva S, dan Precedence Diagram Method (PDM) sebagai jaringan. Hasil perhitungan didapatkan Rencana Anggaran Biaya untuk proyek tersebut adalah Rp. 914.486.100,00 dan durasi pelaksanaannya 91 hari.

References

A. I. Candra, “STUDI KASUS STABILITAS STRUKTUR TANAH LEMPUNG PADA JALAN TOTOK KEROT KEDIRI MENGGUNAKAN LIMBAH KERTAS,†UKaRsT, 2018, doi: 10.30737/ukarst.v2i2.255.

H. R. Agustapraja and Affandi, “PERBANDINGAN ESTIMASI ANGGARAN BIAYA DENGAN METODE SNI DAN BOW PADA PROYEK PEMBANGUNAN GEDUNG D FAKULTAS AGAMA ISLAM UNIVERSITAS ISLAM LAMONGAN,†Ukarst J. Univ. Kadiri Ris. Tek. Sipil, vol. 1, no. 2, pp. 84–93, 2017.

R. Hidayah, A. Ridwan, and Y. C. S. P, “ANALISA PERBANDINGAN MANAJEMEN WAKTU ANTARA PERENCANAAN DAN PELAKSANAAN,†Jurmateks, vol. 1, no. 2, pp. 281–290, 2018.

T. M. Lasmana, P. T. Juwono, and D. Chandrasasih, “Analisis Tinggi Tanggul Ekonomis Sebagai Bangunan Pengendali Banjir Sungai Ciraja Kecamatan Karangpucung Kabupaten Cilacap Provinsi Jawa Tengah,†2017.

D. Oktarina and A. Darmawan, “ANALISA PERBANDINGAN RANGKA ATAP BAJA RINGAN DAN RANGKA ATAP KAYU DARI SEGI ANALISIS STRUKTUR DAN ANGGARAN BIAYA,†J. Konstr., vol. 7, no. 1, pp. 27–36, 2015.

R. O. Purbawa, A. Ridwan, and Y. C. S. P, “PERENCANAAN STRUKTUR ATAS ASRAMA PUTRI DI UNIVERSITAS KADIRI,†Jurmateks, vol. 1, no. 2, pp. 182–191, 2018.

M. Aziz, S. Winarto, Y. C. S. P, and A. I. Candra, “STUDI ANALISA PERENCANAAN PERKERASAN LENTUR DAN RENCANA ANGGARAN BIAYA ( PADA PROYEK JALAN RUAS JALAN TAMBELANGAN – DURJAN KABUPATEN SAMPANG ),†Jurmateks, vol. 2, no. 2, pp. 235–244, 2019.

E. Gardjito, “Pengendalian Jadwal Dan Anggaran Terpadu Dengan Metode Earned Value Analysis Pada Pekerjaan Konstruksi,†UKaRst, vol. 1, no. 1, pp. 47–62, 2017.

W. Arganata, A. D. Limantara, Y. C. S. P, and A. I. Candra, “ANALISIS PERENCANAAN OVERLAY PADA RUAS JALAN CRAKEN-NGULUNGKULON NAMBAK-NGULUNGKULON DENGAN BAHAN ACL PADA STA 0.00-13.345 KECAMATAN MUNJUNGAN KABUPATEN TRENGGALEK,†Jurmateks, vol. 2, no. 1, pp. 121–131, 2019.

I. Santoso, “Analisa Overruns pada Beberapa Tipe Proyek Konstruksi,†Anal. Overruns pada Beberapa Tipe Proy. Konstr., vol. 01, no. 01, pp. 40–48, 1999.

R. D. Prasetyo, Y. Cahyo, and A. Ridwan, “ANALISA PERENCANAAN SISTEM DRAINASE DALAM UPAYA PENANGGULANGAN BANJIR DI KECAMATAN GANDUSARI KABUPATEN TRENGGALEK,†Jurmateks, vol. 2, no. 1, pp. 132–143, 2019.

S. Intan, R. S. Alifen, and L. Arijanto, “ANALISA DAN EVALUASI SISA MATERIAL KONSTRUKSI: SUMBER PENYEBAB, KUANTITAS, DAN BIAYA,†Civ. Eng. Dimens., vol. 7, no. 1, pp. 36–45, 2005.

M. Labombang and S. Qamaria, “Use of Material on The Management Works Embakment Pondo’s River-Poboya,†Infrastruktur, vol. 2, no. 2, pp. 84–95, 2012.

I. Ridkiani, Budiono, and D. Susilowati, “METODE KONSTRUKSI JEMBATAN PRESTRESSED DITINJAU DARI SEGI RENCANA ANGGARAN BIAYA DAN RENCANA WAKTU PELAKSANAAN {Studi kasus Jembatan Rancamaya Proyek TOL BOCIMI (Bogor, Ciawi, Sukabumi)},†pp. 1–13.

A. Kurniawan, J. T. Sipil, and U. Kadiri, “STUDI PERENCANAAN PENINGKATAN JALAN PADA RUAS JALAN JALUR LINTAS SELATAN GIRIWOYO –.â€

Ir. A. Soedrajad. 2008, Analisa Anggaran Biaya Proyek, Nova, Bandung.

Soeharto. 1995, Manajemen Proyek dari Konseptual Sampai Operasional, Edisi Pertama, Erlangga.

Wulfram I. Ervianto. 2003, Manajemen Proyek Konstruksi, Erlangga.

Wulfram I. Ervianto. 2005, Manajemen Proyek Konstruksi, Erlangga.

Gould. 1997, Manajemen Proyek Konstruksi, Erlangga.

Luthan dan Syafriandi. 2006, Aplikasi Microsoft Project,Andi, Yogyakarta.

Mingus. 2004, Management Project,Guna Widya, Jakarta.

Dinas PU Sumber Daya Air UPT PSDA WS Brantas di Kediri, 2019.